Use On Review

1-B-03-UR

Recommended for approval
by the Planning Commission

APPROVE the proposed signage (ten signs), as shown on the attached development plans, in the PC/TO zone, subject to 4 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Approval of signs by the Development Corporation of Knox County.
4. Approval of a Certificate of Appropriateness by the Tennessee Technology Corridor Development Authority (TTCDA) at the January 6, 2003 meeting.

Applicant Request

+

Property Information

+
Location
1305 Centerpoint Blvd

Northeast side of Centerpoint Blvd., northwest side of Lovell Rd.

Commission District 6


Size
4.29 acres

Sector
Northwest County

Land Use Designation? Commercial


Currently on the Property
College

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the proposed signage (ten signs), as shown on the attached development plans, in the PC/TO zone, subject to 4 conditions:
1. Meeting all requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Approval of signs by the Development Corporation of Knox County.
4. Approval of a Certificate of Appropriateness by the Tennessee Technology Corridor Development Authority (TTCDA) at the January 6, 2003 meeting.

With the conditions noted above, this request meets all requirements of the PC zone with a Technology Overlay, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the proposed signage (ten signs), as shown on the attached development plans, in the PC/TO zone, subject to 4 conditions:
Details of Action
1. Meeting all requirements of the Knox County Zoning Ordinance.
2. Meeting all requirements of the Knox County Department of Engineering and Public Works.
3. Approval of signs by the Development Corporation of Knox County.
4. Approval of a Certificate of Appropriateness by the Tennessee Technology Corridor Development Authority (TTCDA) at the January 6, 2003 meeting.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - February 8, 2003 - has passed.

The Process
Applicant

Tusculum College


Case History