Use On Review

11-C-04-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a child day care facility for up to 90 children in the Agricultural zone, subject to 6 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all child daycare licensing requirements of the State of Tennessee.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Adhering to all attached plans and stipulations, as submitted by the applicant for purposes of this review.
6. Preserving all existing trees along the side property lines.

Applicant Request

+

Property Information

+
Location
6904 Tazewell Pike

Southeast side Tazewell Pike, southwest of Henegar Rd.

Commission District 8
Census Tract 64


Size
4 acres

Sector
Northeast County

Land Use Designation? Agricultural / Rural Residential


Currently on the Property
Single family dwelling

Growth Plan
Rural Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a child day care facility for up to 90 children in the Agricultural zone, subject to 6 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all child daycare licensing requirements of the State of Tennessee.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Adhering to all attached plans and stipulations, as submitted by the applicant for purposes of this review.
6. Preserving all existing trees along the side property lines.

With the conditions noted above, this request meets all requirements of the Agricultural zoning district, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a child day care facility for up to 90 children in the Agricultural zone, subject to 6 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Meeting all child daycare licensing requirements of the State of Tennessee.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Adhering to all attached plans and stipulations, as submitted by the applicant for purposes of this review.
6. Preserving all existing trees along the side property lines.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - December 10, 2004 - has passed.

The Process
Applicant

Treehouse Learning Center, LLC


Case History