Details of Action
−
+
1. Approval of the rezoning request for Tax Parcel 027 to PR at a density of up to 5 du/ac by the Knox County Commission (2-G-07-RZ).
2. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (91-1-102)
4. Constructing an east bound left turn lane in W. Emory Rd. at the development entrance subject to approval by the Knox County Department of Engineering and Public Works and the Tennessee Department of Transportation (TDOT). The plans for the turn lane shall be submitted to and approved by County Engineering and TDOT prior to obtaining a grading permit for this project. The timing of the construction of the turn lane shall also be addressed at that time. All work done in the right-of-way of W. Emory Rd. must be done under the supervision of the TDOT.
5. Detailed design plans of the entrance and gate area shall be submitted to the Knox County Department of Engineering and Public Works for approval prior to obtaining a grading permit.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works
7. All sidewalk and walking trail construction to be compliant with the requirements of the Americans With Disabilities Act
8. Obtaining approval of and recording a final plat combining all Tax Parcels into a single lot.
9. Prior to obtaining any certificates of occupancy, establish a homeowners association for the purpose of maintaining the streets, buildings, landscaping, stormwater drainage system and any other commonly held assets.
10. Installation of the landscaping, as shown on the landscape plan, within 6 months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
11. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval within a PR (Planned Residential) district and the criteria for approval of a use on review.
Property Information
−
+
LocationNorth side of W. Emory Rd., east of Yount Rd.
Commission District 6
Size25.52 acres
SectorLand Use Designation? LDR (Low Density Residential)
Currently on the Property
Residence and vacant land
Growth PlanPlanned Growth Area
- Utilities
SewerWest Knox Utility District
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the request for up to 103 attached residential units as shown on the development plan subject to 11 conditions
1. Approval of the rezoning request for Tax Parcel 027 to PR at a density of up to 5 du/ac by the Knox County Commission (2-G-07-RZ).
2. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (91-1-102)
4. Constructing an east bound left turn lane in W. Emory Rd. at the development entrance subject to approval by the Knox County Department of Engineering and Public Works and the Tennessee Department of Transportation (TDOT). The plans for the turn lane shall be submitted to and approved by County Engineering and TDOT prior to obtaining a grading permit for this project. The timing of the construction of the turn lane shall also be addressed at that time. All work done in the right-of-way of W. Emory Rd. must be done under the supervision of the TDOT.
5. Detailed design plans of the entrance and gate area shall be submitted to the Knox County Department of Engineering and Public Works for approval prior to obtaining a grading permit.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works
7. All sidewalk and walking trail construction to be compliant with the requirements of the Americans With Disabilities Act
8. Obtaining approval of and recording a final plat combining all Tax Parcels into a single lot.
9. Prior to obtaining any certificates of occupancy, establish a homeowners association for the purpose of maintaining the streets, buildings, landscaping, stormwater drainage system and any other commonly held assets.
10. Installation of the landscaping, as shown on the landscape plan, within 6 months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
11. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval within a PR (Planned Residential) district and the criteria for approval of a use on review.
Disposition Summary
APPROVE the request for up to 103 attached residential units as shown on the development plan subject to 11 conditions
Details of Action
1. Approval of the rezoning request for Tax Parcel 027 to PR at a density of up to 5 du/ac by the Knox County Commission (2-G-07-RZ).
2. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
3. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (91-1-102)
4. Constructing an east bound left turn lane in W. Emory Rd. at the development entrance subject to approval by the Knox County Department of Engineering and Public Works and the Tennessee Department of Transportation (TDOT). The plans for the turn lane shall be submitted to and approved by County Engineering and TDOT prior to obtaining a grading permit for this project. The timing of the construction of the turn lane shall also be addressed at that time. All work done in the right-of-way of W. Emory Rd. must be done under the supervision of the TDOT.
5. Detailed design plans of the entrance and gate area shall be submitted to the Knox County Department of Engineering and Public Works for approval prior to obtaining a grading permit.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works
7. All sidewalk and walking trail construction to be compliant with the requirements of the Americans With Disabilities Act
8. Obtaining approval of and recording a final plat combining all Tax Parcels into a single lot.
9. Prior to obtaining any certificates of occupancy, establish a homeowners association for the purpose of maintaining the streets, buildings, landscaping, stormwater drainage system and any other commonly held assets.
10. Installation of the landscaping, as shown on the landscape plan, within 6 months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
11. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval within a PR (Planned Residential) district and the criteria for approval of a use on review.