Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Placing a note on the final plat that all structures will have to be located at least 50' from the top of the sinkhole (closed contour area) identified on the plat in the area of Lot 27. Construction within the 50' setback may be permitted if a geotechnical study prepared by a registered engineer states that building within the 50' sinkhole buffer is acceptable and the study is approved by the Knox County Department of Engineering and Public Works. Construction is not permitted within the hatchered contour area of the sinkhole. Engineered footings may be required for any structures within the 50' sinkhole buffer. If a determination is made by the Tennessee Department of Environment and Conservation that this feature is not a sinkhole, this condition would not apply.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Obtaining off-site drainage easements for the outfall from the detention basin as determined by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Certification on the final plat by the applicant's surveyor that there is at a minimum, 300 feet of sight distance in both directions along Bob Kirby Rd.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationWest side of Bob Kirby Rd., north of Dutchtown Rd.
Commission District 5
Size10.09 acres
Sector
Currently on the Property
Residence and vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityLenoir City Utility District
Natuarl GasKnoxville Utilities Board
SewerWest Knox Utility District
TelephoneMetro Group Bell South Telephone
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE variances 1 and 2 because the property's location restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 9 conditions:
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Placing a note on the final plat that all structures will have to be located at least 50' from the top of the sinkhole (closed contour area) identified on the plat in the area of Lot 27. Construction within the 50' setback may be permitted if a geotechnical study prepared by a registered engineer states that building within the 50' sinkhole buffer is acceptable and the study is approved by the Knox County Department of Engineering and Public Works. Construction is not permitted within the hatchered contour area of the sinkhole. Engineered footings may be required for any structures within the 50' sinkhole buffer. If a determination is made by the Tennessee Department of Environment and Conservation that this feature is not a sinkhole, this condition would not apply.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Obtaining off-site drainage easements for the outfall from the detention basin as determined by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Certification on the final plat by the applicant's surveyor that there is at a minimum, 300 feet of sight distance in both directions along Bob Kirby Rd.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Disposition Summary
APPROVE variances 1 and 2 because the property's location restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 9 conditions:
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Placing a note on the final plat that all structures will have to be located at least 50' from the top of the sinkhole (closed contour area) identified on the plat in the area of Lot 27. Construction within the 50' setback may be permitted if a geotechnical study prepared by a registered engineer states that building within the 50' sinkhole buffer is acceptable and the study is approved by the Knox County Department of Engineering and Public Works. Construction is not permitted within the hatchered contour area of the sinkhole. Engineered footings may be required for any structures within the 50' sinkhole buffer. If a determination is made by the Tennessee Department of Environment and Conservation that this feature is not a sinkhole, this condition would not apply.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Obtaining off-site drainage easements for the outfall from the detention basin as determined by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Certification on the final plat by the applicant's surveyor that there is at a minimum, 300 feet of sight distance in both directions along Bob Kirby Rd.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.