Details of Action
−
+
1. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 3.
2. Complying with the Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 1 and 2.
3. Obtaining variances from the Knox County Board of Zoning and Appeals for reduction of the parking stalls from 200 square feet to 180 square feet (10' x 18' parking stall dimension) and for the location of a portion of the parking lots within the required front and side yard setbacks for the BP Zoning District..
4. All landscaping within the sight triangles for the driveways serving the parking lots shall comply with the requirements of the Knox County Zoning Ordinance.
5. Installing the proposed landscaping as shown on the revised landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
6. Meeting all applicable requirements of the approved concept subdivision plan.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review in the BP/TO and OB/TO Zones.
Property Information
−
+
Location1720 Schaeffer Rd
Northeast side of Schaeffer Rd., north of Lovell Rd
Commission District 6
Size23.34 acres
Sector
Growth PlanPlanned Growth Area
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a 3 lot subdivision with 5 office buildings with a total building area of 68,000 square feet within the BP portion of the site, subject to 7 conditions.
1. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 3.
2. Complying with the Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 1 and 2.
3. Obtaining variances from the Knox County Board of Zoning and Appeals for reduction of the parking stalls from 200 square feet to 180 square feet (10' x 18' parking stall dimension) and for the location of a portion of the parking lots within the required front and side yard setbacks for the BP Zoning District..
4. All landscaping within the sight triangles for the driveways serving the parking lots shall comply with the requirements of the Knox County Zoning Ordinance.
5. Installing the proposed landscaping as shown on the revised landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
6. Meeting all applicable requirements of the approved concept subdivision plan.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review in the BP/TO and OB/TO Zones.
Disposition Summary
APPROVE the development plan for a 3 lot subdivision with 5 office buildings with a total building area of 68,000 square feet within the BP portion of the site, subject to 7 conditions.
Details of Action
1. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 3.
2. Complying with the Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA) for the development and signage plans for Lot 1 and 2.
3. Obtaining variances from the Knox County Board of Zoning and Appeals for reduction of the parking stalls from 200 square feet to 180 square feet (10' x 18' parking stall dimension) and for the location of a portion of the parking lots within the required front and side yard setbacks for the BP Zoning District..
4. All landscaping within the sight triangles for the driveways serving the parking lots shall comply with the requirements of the Knox County Zoning Ordinance.
5. Installing the proposed landscaping as shown on the revised landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
6. Meeting all applicable requirements of the approved concept subdivision plan.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review in the BP/TO and OB/TO Zones.