Subdivision

Final Plat

12-SB-25-F

To be heard December 11, 2025Agenda Item No. 20

Planning Staff Recommendation

Approve the final plat per Sections 2.08.A and 2.10.F of the Subdivision Regulations, which require the plat to be in substantial conformance with the concept plan. Planning staff affirms the plat conforms to the overall layout and design of the concept plan approved by the Planning Commission on 5/8/2025 as Planning Case 5-SB-25-C.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
FINAL PLAT OF STRAWBERRY HILLS SUBDIVISION, PHASE III SECTION C
Lots
64 (Split)
Residential?
Yes - SF

Property Information

+
Location
0 SUN BLOSSOM LN

West of Brakebill Rd, south of Hammer Rd

Commission District 8


Size
35.38 acres

Place Type Designation
TN (Traditional Neighborhood), HP (Hillside Ridgetop Protection)

Currently on the Property
Single Family Residential, Multifamily Residential

Growth Plan
Urban Growth Area (Outside City Limits)

Fire Department / District
Rural Metro Fire

Case Notes

+

Staff Recommendation
Approve the final plat per Sections 2.08.A and 2.10.F of the Subdivision Regulations, which require the plat to be in substantial conformance with the concept plan. Planning staff affirms the plat conforms to the overall layout and design of the concept plan approved by the Planning Commission on 5/8/2025 as Planning Case 5-SB-25-C.
The plat closure review was completed after the corrections deadline. Planning staff has allowed the plat to remain on the agenda in accordance with Section 2.10.C.6, which states the nine-day final plat correction deadline may be waived with just cause. In this case, the remaining revisions would not change the general subdivision or lot layout. Additionally, revisions to the final plat were submitted in time to be included in the Planning Commission documentation.

What's next?

+
Final Plat appeals will be heard by the Planning Commission.
Appeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

FINAL PLAT OF STRAWBERRY HILLS SUBDIVISION, PHASE III SECTION C

Ethan I Phillips


Case History