Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
B & B Builders - Dry Gap Pike
Lots
93 (Split)
Proposed Density
3.7 du/ac
Residential?
Yes - SF

Variances

VARIANCES:

1) REDUCTION OF INTERSECTION SPACING ON POND GAP PIKE BETWEEN ROAD 'A' AND AUTUMN PATH LANE FROM 300 FEET TO 295.6 FEET.
2) REDUCTION OF THE MINIMUM CONNECTING VERTICAL CURVE K VALUE ON ROAD ?A? AT STA 2+50, FROM 25 TO 15.

ALTERNATE DESIGN STANDARDS REQUIRING PLANNING COMMISSION APPROVAL:

1) REDUCTION OF MINIMUM HORIZONTAL CURVE RADIUS ON ROAD 'B' AT STA 2+50 FROM 250' TO 230'
2) REDUCTION OF MINIMUM HORIZONTAL CURVE RADIUS ON ROAD 'B' AT STA 6+00 FROM 250' TO 200'

ALTERNATE DESIGN STANDARDS APPROVED BY KNOX COUNTY ENGINEERING AND PUBLIC WORKS:

1) INCREASE MINIMUM INTERSECTION GRADE AT ROAD 'A', STA 0+13 TO STA 2+50, FROM 1% TO 2%
2) INCREASE MINIMUM INTERSECTION GRADE AT ROAD 'B', STA 0+13 TO STA 2+25, FROM 1% TO 3%
3) INCREASE MINIMUM INTERSECTION GRADE AT ROAD 'C', STA 0+13 TO STA 1+00, FROM 1% TO 2%


Property Information

+
Location
1611 Dry Gap Pk.

Southwest side of Dry Gap Pk., north of Branch Field Ln.

Commission District 7


Size
25.15 acres

Sector
North County

Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE variance 1-2 and alternate design standard 1-2 based on the recommendations of the Knox County Department of Engineering and Public Works and because the site conditions restrict compliance with the Subdivision Regulations and the proposed varia
1. Connection to sanitary sewer and meeting any other relevant requirements of the utility provider.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord 91-1-102).
3. Installation of all sidewalks required by the Knox County sidewalk ordinance (Ord 19-12-101) or as otherwise required by Knox County Engineering and Public Works.
4. Providing an access easement, as shown on the Concept Plan, for the existing driveway on the adjacent property (parcel 047-24102) that crosses the subject property through the common area south of Road ?A? along Dry Gap Pike and lots 88-93.
5. Implementation of the road improvement recommendations outlined in the Dry gap Pike Subdivision Transportation Impact Study (TIS) prepared by Ajax Engineering (September 17, 2020), as revised, and reviewed and approved by Planning Commission staff and Knox County Engineering and Public Works (see Exhibit A). The design details of the road improvements shall be worked out with the Knox County Department of Engineering and Public Works during the design plan stage for the subdivision and the improvements shall be completed prior to certification of the final plat for recording.
6. Revising Road ?A? at the Dry Gap Pike intersection to work with the proposed profile and pavement edge of the pending Dry Gap Pike road widening project.
7. Revising the grade of Road ?A? at the Dry Gap Pike intersection to meet the crosswalk requirements of ADA and the Knox County Department of Engineering and Public Works.
8. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
9. All closed contours/sinkholes and the 50' setback around the feature shall be shown on the final plat. Building construction within the 50' setback may be permitted if a geotechnical study prepared by a registered engineer states that building within the 50' sinkhole buffer is acceptable and the study is approved by the Knox County Department of Engineering and Public Works. The geotechnical study must be completed and submitted to Knox County Department of Engineering and Public Works prior to submission of the final plat for any lots that do not have a building area outside of the 50' setback area. A 5' drainage easement extending outside of the uppermost closed contour is required. Building construction is not permitted within the hatchered contour area of the sinkhole or the drainage easement. Engineered footings may be required for any structures within the 50' sinkhole buffer.
10. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for the maintenance of the common areas and stormwater/drainage facilities.
11. Submitting the certification of design plan approval form to Planning Commission staff prior to final plat review by the Planning Commission or Planning staff, as required by the Knoxville-Knox County Subdivision Regulations (Section 2.08, Design Plan -- Major Subdivisions).
Disposition Summary
APPROVE variance 1-2 and alternate design standard 1-2 based on the recommendations of the Knox County Department of Engineering and Public Works and because the site conditions restrict compliance with the Subdivision Regulations and the proposed varia

What's next?

+
After the Planning Commission
Because of its location in the County, appeals will be heard by Knox County Chancery Court.