Design Review Board
Level 3: Construction of new building/structure
2-B-08-DT
This case has been appealed
Staff Recommendation
Location430 Union Ave
Applicant Request
The proposed project is a four story office building for Home Federal Offices, with two stories of underground employee parking on the block between Union Avenue and Clinch Avenue along Walnut Street. The total area of the building is 59,000 +/- square feet, and area of the parking garage is 34,000 +/- square feet. There is a to story portion adjacent to the Grand Union Building which may have a roof terrace/garden. The main entries are from Union and Walnut with a canopy that wraps the corner of the building. The entrance to the upper level parking is from Walnut Street, with the entrance to the lower level parking and the surface lot from Clinch Avenue.
The exterior of the building is granite, limestone, brick, with copper panels inset in a painted steel window system and copper parapet wall. The interior will house office space for Home Federal Bank, but will not have any banking facilities or automated teller machines. The mechanical consists of three air handling units screened from view on the roof. The roof will be a thermo-plastic membrane roofing system
The exterior of the building is granite, limestone, brick, with copper panels inset in a painted steel window system and copper parapet wall. The interior will house office space for Home Federal Bank, but will not have any banking facilities or automated teller machines. The mechanical consists of three air handling units screened from view on the roof. The roof will be a thermo-plastic membrane roofing system
Staff Comments
The proposed structure and site plan meet the guidelines for new structures except for the following guidelines in question:
A.1g - Consolidate curb-cuts and locate driveways near mid-block, when necessary; alley access should be provided for service and parking, if feasible.
* There are two proposed parking lot entrances, with each providing access to different levels of parking. There is on entrance near the intersection of Walnut and Clinch and one mid-block along Walnut.
A.3a - Create parking garages that do not contain blank walls. Allow for future commercial uses that may not be feasible at the time of construction.
* As seen in the attached site plan and perspective (pages A.1 and A.8) from Union and Clinch, there is "Surface Parking" to be built on the corner of Clinch and Walnut. This is actually a ramp that will provide parking and access to the ground level of parking under the new building. This ramp is open and does not have a blank building wall but it does have a small retaining wall that will create a void. The ramp will also reduce the feasibility of future commercial uses on the corner of Clinch and Walnut. There is already one other corner at this intersection that has a blank wall and very low probability of commercial use.
A.3c - Locate surface parking lots to the side or rear of building. No surface parking lots should be created in front of buildings. (page 7)
* In relation to the "Surface Parking" as mentioned above, though this parking is behind the building as the guidelines prescribe, the parking and access is along a parallel avenue and pedestrian connector.
B.2a - Set buildings back five feet in order to provide wider sidewalk space when new construction in non-historic areas is to be more than half the length of the block. (page 12)
* This building will occupy a little less than half the block. The C-2 zoning district requires a 5 ft front setback along vehicular streets (Article 4, Section 8 E.1). The D-1 Overlay District does allow for the Downtown Design Review Board to reduce this requirement when a development has been conceived to respect the historic context of the block, provide greater pedestrian activity at sidewalk level or meet other provisions of the guidelines (Article 4, Section 26 C). The sidewalks are adequate for tree planting and clear pedestrian passage.
B.4a - Encourage first floor uses that draw walk-in traffic; businesses that do not require pedestrian traffic should be located on other floors. (page 14)
* This building is currently planned solely as office space for Home Federal. This building will not have a bank branch or ATM.
Features of note of the proposal:
* The portion of the building closest to the Grand Union is two stories to allow the windows facing the new building to retain a view.
* There may be a roof terrace/garden on the two story portion.
* There are 2 stories of parking under the building.
* The sidewalks will be no less than approximately 14 ft along Union and no less than approximately 7 ft along Walnut, with the sidewalk mostly approximately 12 ft.
* The upper floor of parking has access from approximately the current surface parking entrance along Walnut Street.
*The ground floor along Walnut will be mainly a lobby which will have a low likelihood of having window coverings. This will for visibility into the building from the sidewalk.
* No signage was submitted for approval.
A.1g - Consolidate curb-cuts and locate driveways near mid-block, when necessary; alley access should be provided for service and parking, if feasible.
* There are two proposed parking lot entrances, with each providing access to different levels of parking. There is on entrance near the intersection of Walnut and Clinch and one mid-block along Walnut.
A.3a - Create parking garages that do not contain blank walls. Allow for future commercial uses that may not be feasible at the time of construction.
* As seen in the attached site plan and perspective (pages A.1 and A.8) from Union and Clinch, there is "Surface Parking" to be built on the corner of Clinch and Walnut. This is actually a ramp that will provide parking and access to the ground level of parking under the new building. This ramp is open and does not have a blank building wall but it does have a small retaining wall that will create a void. The ramp will also reduce the feasibility of future commercial uses on the corner of Clinch and Walnut. There is already one other corner at this intersection that has a blank wall and very low probability of commercial use.
A.3c - Locate surface parking lots to the side or rear of building. No surface parking lots should be created in front of buildings. (page 7)
* In relation to the "Surface Parking" as mentioned above, though this parking is behind the building as the guidelines prescribe, the parking and access is along a parallel avenue and pedestrian connector.
B.2a - Set buildings back five feet in order to provide wider sidewalk space when new construction in non-historic areas is to be more than half the length of the block. (page 12)
* This building will occupy a little less than half the block. The C-2 zoning district requires a 5 ft front setback along vehicular streets (Article 4, Section 8 E.1). The D-1 Overlay District does allow for the Downtown Design Review Board to reduce this requirement when a development has been conceived to respect the historic context of the block, provide greater pedestrian activity at sidewalk level or meet other provisions of the guidelines (Article 4, Section 26 C). The sidewalks are adequate for tree planting and clear pedestrian passage.
B.4a - Encourage first floor uses that draw walk-in traffic; businesses that do not require pedestrian traffic should be located on other floors. (page 14)
* This building is currently planned solely as office space for Home Federal. This building will not have a bank branch or ATM.
Features of note of the proposal:
* The portion of the building closest to the Grand Union is two stories to allow the windows facing the new building to retain a view.
* There may be a roof terrace/garden on the two story portion.
* There are 2 stories of parking under the building.
* The sidewalks will be no less than approximately 14 ft along Union and no less than approximately 7 ft along Walnut, with the sidewalk mostly approximately 12 ft.
* The upper floor of parking has access from approximately the current surface parking entrance along Walnut Street.
*The ground floor along Walnut will be mainly a lobby which will have a low likelihood of having window coverings. This will for visibility into the building from the sidewalk.
* No signage was submitted for approval.
Applicant
Planning Staff
Email: contact@knoxplanning.org
Barber McMurry Architects
Planning Staff
Mike Carberry
Phone: 215-2500Email: contact@knoxplanning.org
Case History
- September 13, 2007
Date Filed
- September 25, 2007
Date Filed
- October 8, 2007
Date Filed
- October 17, 2007
Date Filed
- November 6, 2007
Date Filed
- November 7, 2007
Date Filed
- November 26, 2007
- December 4, 2007
Date Filed
- December 6, 2007
Date Filed
- December 10, 2007
Date Filed
- December 19, 2007
- January 3, 2008
Date Filed
- January 8, 2008
Date Filed
- January 16, 2008
- January 29, 2008
Date Filed
- February 1, 2008
Date Filed
- February 20, 2008
- October 15, 2008
Date Filed
- October 21, 2008
Date Filed
- November 14, 2008
Date Filed
- December 5, 2008
Date Filed
- December 15, 2008
- January 8, 2009
Date Filed
- November 2, 2009
Date Filed
- November 5, 2009
Date Filed
- November 6, 2009
Date Filed
- November 13, 2009
Date Filed
- November 18, 2009
- November 25, 2009
Date Filed
- December 2, 2009
Date Filed
- December 7, 2009
Date Filed
- December 16, 2009
- January 5, 2010
Date Filed
- January 20, 2010
- January 25, 2010
Date Filed
Appealed
- February 17, 2010
- September 23, 2010
Date Filed
- September 28, 2010
Date Filed
- September 30, 2010
Date Filed
- October 1, 2010
Date Filed
- October 20, 2010
- November 22, 2010
Date Filed
- November 23, 2010
- December 30, 2010
Date Filed
- January 28, 2011
Date Filed
- February 16, 2011
- September 16, 2011
Date Filed
- September 26, 2011
Date Filed
- September 30, 2011
Date Filed
- October 3, 2011
Date Filed
- October 11, 2011
Date Filed
- October 12, 2011
Date Filed
- October 19, 2011
- October 24, 2011
Date Filed
- November 2, 2011
Date Filed
- November 7, 2011
Date Filed
- November 16, 2011
- February 6, 2012
Date Filed
- February 15, 2012
- September 20, 2012
Date Filed
- September 26, 2012
Date Filed
- October 3, 2012
Date Filed
- October 4, 2012
- October 12, 2012
Date Filed
- October 17, 2012
- November 1, 2012
Date Filed
- November 5, 2012
Date Filed
- November 14, 2012
- November 29, 2012
Date Filed
- December 4, 2012
Date Filed
- December 5, 2012
Date Filed
- December 10, 2012
- December 19, 2012
- February 12, 2013
Date Filed
- February 20, 2013
- May 15, 2013
- May 17, 2013
Appealed
- September 27, 2013
Date Filed
- October 4, 2013
Date Filed
- October 9, 2013
Date Filed
- October 16, 2013
- October 21, 2013
Date Filed
- October 30, 2013
Date Filed
- November 7, 2013
Date Filed
- November 15, 2013
Date Filed
- November 20, 2013
- November 25, 2013
- November 27, 2013
Date Filed
- December 5, 2013
Date Filed
- December 18, 2013
- January 10, 2014
Date Filed
- January 22, 2014
Date Filed
- January 23, 2014
- January 31, 2014
Date Filed
- February 19, 2014
- September 16, 2014
Date Filed
- September 25, 2014
Date Filed
- October 6, 2014
Date Filed
- October 7, 2014
- October 15, 2014
- October 27, 2014
Date Filed
- October 31, 2014
Date Filed
- November 7, 2014
Date Filed
- November 10, 2014
Date Filed
- November 14, 2014
Date Filed
- November 19, 2014
- November 26, 2014
Date Filed
- December 3, 2014
Date Filed
- December 5, 2014
Date Filed
- December 10, 2014
Date Filed
- December 17, 2014
- January 8, 2015
Date Filed
- January 21, 2015
- January 22, 2015
Date Filed
- February 18, 2015
- March 18, 2015
- April 15, 2015
- October 1, 2015
Date Filed
- October 2, 2015
Date Filed
- October 9, 2015
Date Filed
- October 16, 2015
Date Filed
- October 21, 2015
- October 22, 2015
Date Filed
- October 26, 2015
Date Filed
- October 29, 2015
Date Filed
- October 30, 2015
Date Filed
- November 18, 2015
- November 19, 2015
Date Filed
- November 25, 2015
Date Filed
- November 30, 2015
Date Filed
- December 2, 2015
- December 3, 2015
Date Filed
- December 16, 2015
- December 17, 2015
Date Filed
- December 23, 2015
- December 30, 2015
Date Filed
- February 5, 2016
Date Filed
- September 26, 2016
Date Filed
- October 5, 2016
Date Filed
- October 6, 2016
Date Filed
- October 19, 2016
- November 3, 2016
Date Filed
- November 9, 2016
Date Filed
- November 17, 2016
- December 14, 2016
- December 29, 2016
Date Filed
- January 6, 2017
Date Filed
- January 13, 2017
Date Filed
- January 18, 2017
- January 27, 2017
Date Filed
- February 1, 2017
- February 15, 2017
- September 28, 2017
Date Filed
- October 18, 2017
- October 23, 2017
Date Filed
- October 30, 2017
Date Filed
- November 15, 2017
- November 16, 2017
Date Filed
- November 27, 2017
Date Filed
- November 30, 2017
Date Filed
- December 4, 2017
Date Filed
- December 5, 2017
Date Filed
- December 20, 2017
- December 28, 2017
Date Filed
- December 29, 2017
Date Filed
- January 9, 2018
Date Filed
- January 17, 2018
Date Filed
- February 21, 2018
- March 6, 2018
- September 24, 2018
Date Filed
- October 5, 2018
Date Filed
- October 12, 2018
Date Filed
- October 15, 2018
Date Filed
- October 17, 2018
- October 19, 2018
- October 26, 2018
- November 5, 2018
Date Filed
- November 14, 2018
- December 4, 2018
Date Filed
- December 17, 2018
Date Filed
- December 19, 2018
- December 20, 2018
Date Filed
- January 4, 2019
Date Filed
- January 16, 2019
- January 23, 2019
Date Filed
- February 20, 2019
- September 27, 2019
Date Filed
- October 16, 2019
- October 22, 2019
Date Filed
- November 1, 2019
Date Filed
- November 13, 2019
Date Filed
- November 18, 2019
Date Filed
- November 19, 2019
Date Filed
- November 20, 2019
- November 21, 2019
- December 18, 2019
- January 2, 2020
Date Filed
- January 6, 2020
- January 22, 2020
Date Filed
- February 19, 2020
- September 9, 2020
Date Filed
- September 28, 2020
Date Filed
- October 5, 2020
Date Filed
- October 21, 2020
- October 26, 2020
Date Filed
- October 30, 2020
Date Filed
- November 18, 2020
Date Filed
- November 23, 2020
Date Filed
- November 30, 2020
Date Filed
- December 16, 2020
- December 28, 2020
Date Filed
- January 20, 2021
- February 1, 2021
Date Filed
- February 17, 2021
- October 5, 2021
Date Filed
- October 8, 2021
Date Filed
- October 20, 2021
- November 1, 2021
Date Filed
- November 17, 2021
- December 7, 2021
Date Filed
- December 15, 2021
- January 4, 2022
Date Filed
- January 19, 2022
- January 28, 2022
Date Filed
- March 16, 2022
- September 19, 2022
Date Filed
- September 21, 2022
- September 30, 2022
Date Filed
- October 19, 2022
- October 28, 2022
Date Filed
- October 31, 2022
Date Filed
- November 16, 2022
- November 23, 2022
Date Filed
- December 2, 2022
Date Filed
- December 7, 2022
Date Filed
- December 21, 2022
- January 3, 2023
Date Filed
- January 18, 2023
- September 20, 2023
Date Filed
- October 2, 2023
Date Filed
- October 18, 2023
- October 24, 2023
Date Filed
- November 15, 2023
- December 4, 2023
Date Filed
- December 20, 2023
- December 22, 2023
Date Filed
- January 23, 2024
Date Filed
- February 21, 2024
- September 16, 2024
Date Filed
- October 16, 2024
- October 18, 2024
Date Filed
- October 30, 2024
Date Filed
- November 1, 2024
Date Filed
- November 20, 2024
- November 21, 2024
Date Filed
- December 4, 2024
Date Filed
- December 18, 2024
- December 19, 2024
Date Filed
- January 15, 2025
- January 30, 2025
Date Filed
- February 19, 2025