Subdivision

Concept Plan

2-SA-02-C

Recommended for approval
by the Planning Commission

APPROVE variances 1-3 because of topography and the proposed variances will not create a traffic hazard
APPROVE the concept plan subject to 13 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville (Ord. 0-280-90).
3. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
4. Placing a note on the final plat that no dwellings will be located within 50' of the hatched contour of the sinkhole in the southeast corner of this site.
5. Eliminating lots 196 - 198 and making them part of the common area.
6. Sidewalks being constructed either as a walking trail around the perimeter of the project as shown on the concept plan with pedestrian accesses to be provided approximately every 500' from the street system and multiple pedestrian access points to the proposed clubhouse and common area. Or the developer may provide a sidewalk system along one side of every street within the development with additional pedestrian access points to the clubhouse and common area. Sidewalks will be constructed to a minimum width of 5'.
7. Final approval by the Knoxville City Council to rezone this site to RP-1 at a density equal to or greater than the proposed development density.
8. Certification on the final plat by the applicant's engineer that there is 400' of sight distance in both directions looking onto E. Beaver Creek Dr. from Street A in this development.
9. Construction of the left turn lane and the right turn deceleration lane as called for in the traffic impact study per the requirements of the Knox County Dept. of Engineering and Public Works and the Knoxville City Engineer.
10. Design of the improvements called for in the revised traffic impact study being the responsibility of the applicant as required by the Knox County Dept. of Engineering and Public Works.
11. Meeting all applicable requirements of the Knoxville City Engineer and the Knox County Dept. of Engineering and Public Works.
12. Meeting all requirements of the approved use on review development plan.
13. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff.

Applicant Request

+
Subdivision
MPM Development on E. Beaver Creek Dr.
Lots
222 (Split)
Proposed Density
6.71 du/ac

Variances

1. Horizontal curve radius from 250' to 200' at sta. 9+50 of Road E.
2. Horizontal curve radius from 250' to 200' at sta. 5+50 of Road E.
3. Vertical curve variance from 250' to 140 at sta. 1+25 of Road A.


Property Information

+
Location
Northwest side of E. Beaver Creek Dr., northeast side of I-75

Council District 5


Size
33.54 acres

Sector
North County

Currently on the Property
One single family dwelling and vacant

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE variances 1-3 because of topography and the proposed variances will not create a traffic hazard

APPROVE the concept plan subject to 13 conditions

1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville (Ord. 0-280-90).
3. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
4. Placing a note on the final plat that no dwellings will be located within 50' of the hatched contour of the sinkhole in the southeast corner of this site.
5. Eliminating lots 196 - 198 and making them part of the common area.
6. Sidewalks being constructed either as a walking trail around the perimeter of the project as shown on the concept plan with pedestrian accesses to be provided approximately every 500' from the street system and multiple pedestrian access points to the proposed clubhouse and common area. Or the developer may provide a sidewalk system along one side of every street within the development with additional pedestrian access points to the clubhouse and common area. Sidewalks will be constructed to a minimum width of 5'.
7. Final approval by the Knoxville City Council to rezone this site to RP-1 at a density equal to or greater than the proposed development density.
8. Certification on the final plat by the applicant's engineer that there is 400' of sight distance in both directions looking onto E. Beaver Creek Dr. from Street A in this development.
9. Construction of the left turn lane and the right turn deceleration lane as called for in the traffic impact study per the requirements of the Knox County Dept. of Engineering and Public Works and the Knoxville City Engineer.
10. Design of the improvements called for in the revised traffic impact study being the responsibility of the applicant as required by the Knox County Dept. of Engineering and Public Works.
11. Meeting all applicable requirements of the Knoxville City Engineer and the Knox County Dept. of Engineering and Public Works.
12. Meeting all requirements of the approved use on review development plan.
13. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff.
Disposition Summary
APPROVE variances 1-3 because of topography and the proposed variances will not create a traffic hazard
APPROVE the concept plan subject to 13 conditions

Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville (Ord. 0-280-90).
3. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
4. Placing a note on the final plat that no dwellings will be located within 50' of the hatched contour of the sinkhole in the southeast corner of this site.
5. Eliminating lots 196 - 198 and making them part of the common area.
6. Sidewalks being constructed either as a walking trail around the perimeter of the project as shown on the concept plan with pedestrian accesses to be provided approximately every 500' from the street system and multiple pedestrian access points to the proposed clubhouse and common area. Or the developer may provide a sidewalk system along one side of every street within the development with additional pedestrian access points to the clubhouse and common area. Sidewalks will be constructed to a minimum width of 5'.
7. Final approval by the Knoxville City Council to rezone this site to RP-1 at a density equal to or greater than the proposed development density.
8. Certification on the final plat by the applicant's engineer that there is 400' of sight distance in both directions looking onto E. Beaver Creek Dr. from Street A in this development.
9. Construction of the left turn lane and the right turn deceleration lane as called for in the traffic impact study per the requirements of the Knox County Dept. of Engineering and Public Works and the Knoxville City Engineer.
10. Design of the improvements called for in the revised traffic impact study being the responsibility of the applicant as required by the Knox County Dept. of Engineering and Public Works.
11. Meeting all applicable requirements of the Knoxville City Engineer and the Knox County Dept. of Engineering and Public Works.
12. Meeting all requirements of the approved use on review development plan.
13. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff.

What's next?

+
After the Planning CommissionAppeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

MPM Development on E. Beaver Creek Dr.

MPM Development


Case History