Recommended for approval by the Planning Commission
See case notes below
N/A
Northwest terminus of Kemp Fain Ln.
Commission District 6
Land Use Designation? TP (Technology Park)
Staff recommends approval of this request for a Certificate of Appropriateness for a building permit, subject to the following conditions:
1) Installation of all landscaping as shown on development plan within six months of the issuance of an occupancy permit, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) If signage is desired in the future, a signage package would need to be submitted and would be required to meet all applicable requirements of the TTCDA.
Vote