Use On Review

3-J-22-UR

Approved by the Planning Commission

Approve the request for a manufacturing facility in the BP (Business and Technology Park) zone, subject to three conditions.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
10601 Kemp Fain Ln.

At the Northwest terminus of Kemp Fain Lane

Commission District 6


Size
12.15 acres

Sector
Northwest County

Land Use Designation? TP (Technology Park)


Currently on the Property
AgForVac (Agriculture/Forestry/Vacant Land)

Growth Plan
Planned Growth Area

Case Notes

+
Approve the request for a manufacturing facility in the BP (Business and Technology Park) zone, subject to three conditions.

1) Installation of all landscaping as shown on development plan within six months of the issuance of an occupancy permit, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.

What's next?

+
After the Planning Commission
Because of its location in the County, appeals will be heard by Knox County Board of Zoning Appeals.
Appeal to Knox County Code Administration Department by: April 11, 2022The process
Applicant

Partners Development