Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Dept.
2. Obtaining final approval from the City Engineer of a drainage and erosion control plan and obtaining any required off site drainage easements prior to commencing any further grading on this site.
3. The driveways from the Wilson and Sullivan properties be tied to the entrance road of this development at a point greater than 25' back from the intersection or being relocated to a point greater than 50' from the proposed entrance.
4. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville, Ord. O-280-90.
5. Installation of landscaping as shown on the development plan within six months after the issuance of an occupancy permit
Penco Contractors
3-L-01-UR
Page 2
for each dwelling. The landscaping proposed for the entrance to the development is to be installed within six months of the issuance of the first occupancy permit within the development.
6. The swimming pool and amenities area is to be built within one year after issuance of the first occupancy permit within this development.
7. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
8. Meeting all applicable requirements of the Knoxville Department of Engineering.
9. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
10. A revised site plan and land survey reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
Property Information
−
+
LocationNorth side Piney Grove Church Rd., southwest of Tennyson Dr.
Council District 3
Size12.24 acres
Planning SectorNorthwest City
Currently on the Property
Vacant
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Disposition Summary
APPROVE the development plan for up to 72 attached residential condominium units as shown on the development plan subject to 10 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Dept.
2. Obtaining final approval from the City Engineer of a drainage and erosion control plan and obtaining any required off site drainage easements prior to commencing any further grading on this site.
3. The driveways from the Wilson and Sullivan properties be tied to the entrance road of this development at a point greater than 25' back from the intersection or being relocated to a point greater than 50' from the proposed entrance.
4. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville, Ord. O-280-90.
5. Installation of landscaping as shown on the development plan within six months after the issuance of an occupancy permit
Penco Contractors
3-L-01-UR
Page 2
for each dwelling. The landscaping proposed for the entrance to the development is to be installed within six months of the issuance of the first occupancy permit within the development.
6. The swimming pool and amenities area is to be built within one year after issuance of the first occupancy permit within this development.
7. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
8. Meeting all applicable requirements of the Knoxville Department of Engineering.
9. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
10. A revised site plan and land survey reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
Staff Recommendation
APPROVE the development plan for up to 72 attached residential condominium units as shown on the development plan subject to 10 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Dept.
2. Obtaining final approval from the City Engineer of a drainage and erosion control plan and obtaining any required off site drainage easements prior to commencing any further grading on this site.
3. The driveways from the Wilson and Sullivan properties be tied to the entrance road of this development at a point greater than 25' back from the intersection or being relocated to a point greater than 50' from the proposed entrance.
4. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knoxville, Ord. O-280-90.
5. Installation of landscaping as shown on the development plan within six months after the issuance of an occupancy permit
Penco Contractors
3-L-01-UR
Page 2
for each dwelling. The landscaping proposed for the entrance to the development is to be installed within six months of the issuance of the first occupancy permit within the development.
6. The swimming pool and amenities area is to be built within one year after issuance of the first occupancy permit within this development.
7. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
8. Meeting all applicable requirements of the Knoxville Department of Engineering.
9. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
10. A revised site plan and land survey reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.