APPROVE the development plan for up 16 attached residential condominium dwellings subject to 8 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County, (Ord. 91-1-102).
3. Installation of landscaping as shown on the development plan within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Access is to be limited to one point and at the proposed median cut in Middlebrook Pike. The other proposed access is to be deleted.
5. Obtaining a driveway connection permit from the Tennessee Dept. of Transportation.
6. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance




Middlebrook Partnership
4-H-01-UR
Page 2


of any building permits.

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.

Applicant Request

+

Property Information

+
Location
9432 Middlebrook Pike

South side of Middlebrook Pike., west of Durham Rd.

Commission District 5


Size
4.10 acres

Sector
Northwest County

Currently on the Property
Vacant

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for up 16 attached residential condominium dwellings subject to 8 conditions.
1. Meeting all applicable requirements of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County, (Ord. 91-1-102).
3. Installation of landscaping as shown on the development plan within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Access is to be limited to one point and at the proposed median cut in Middlebrook Pike. The other proposed access is to be deleted.
5. Obtaining a driveway connection permit from the Tennessee Dept. of Transportation.
6. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance




Middlebrook Partnership
4-H-01-UR
Page 2


of any building permits.

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.
Disposition Summary
APPROVE the development plan for up 16 attached residential condominium dwellings subject to 8 conditions.
Details of Action
1. Meeting all applicable requirements of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County, (Ord. 91-1-102).
3. Installation of landscaping as shown on the development plan within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Access is to be limited to one point and at the proposed median cut in Middlebrook Pike. The other proposed access is to be deleted.
5. Obtaining a driveway connection permit from the Tennessee Dept. of Transportation.
6. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance




Middlebrook Partnership
4-H-01-UR
Page 2


of any building permits.

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - May 12, 2001 - has passed.

The Process
Applicant

Middlebrook Partnership


Case History