Details of Action
−
+
1) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
2) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Property Information
−
+
Location10225 Bluegrass Rd
Northwest side of Bluegrass Rd., north of Northshore Dr., southwest of Garland Rd.
Commission District 5
Size4.51 acres
Sector
Currently on the Property
Single-family residences
Growth PlanPlanned Growth Area
Case Notes
−
+
Staff Recommendation
APPROVE the development plan fo a 195 foot monopole telecommunications tower subject to 5 conditions.
1) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
2) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.
Disposition Summary
APPROVE the development plan fo a 195 foot monopole telecommunications tower subject to 5 conditions
Details of Action
1) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
2) Since the FAA does not require any lighting for this facility, there shall be no lighting on the tower.
3) Meeting all applicable requirements of the Knox County Zoning Ordinance.
4) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5) A revised site plan reflecting the conditions of approval must be submitted to MPC prior to the issuance of building permits for the project.
With the conditions noted, the request meets all requirements for approval of a use-on-review.