Details of Action
−
+
1. Meeting all requirements of the approved concept plan.
2. Installation of the landscaping in the areas of the site that will not be directly impacted by the construction of the dwelling units within 60 days after the completion of the installation of utilities and road construction for each phase of the project. All remaining landscaping is to be installed incrementally as each unit is completed or within 6 months of the issuance of the occupancy permit for each unit.
3. Establishment of a homeowners association for the purpose of assessing fees for the maintenance of the exterior of the dwellings, grounds, clubhouse, common areas and all other assets of the association.
4. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
5. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to the issuance of any grading permits for this project.
6. No commercial uses being proposed as part of this project as may be permitted with MPC approval in the RP-1 District. (See attached letter from the applicant's attorney).
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a Use on Review.
Case Notes
−
+
Disposition Summary
APPROVE the development plan for up to145 attached single family residential units on individual lots subject to 6 conditions
Details of Action
1. Meeting all requirements of the approved concept plan.
2. Installation of the landscaping in the areas of the site that will not be directly impacted by the construction of the dwelling units within 60 days after the completion of the installation of utilities and road construction for each phase of the project. All remaining landscaping is to be installed incrementally as each unit is completed or within 6 months of the issuance of the occupancy permit for each unit.
3. Establishment of a homeowners association for the purpose of assessing fees for the maintenance of the exterior of the dwellings, grounds, clubhouse, common areas and all other assets of the association.
4. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
5. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to the issuance of any grading permits for this project.
6. No commercial uses being proposed as part of this project as may be permitted with MPC approval in the RP-1 District. (See attached letter from the applicant's attorney).
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a Use on Review.
Staff Recommendation
APPROVE the development plan for up to145 attached single family residential units on individual lots subject to 6 conditions
1. Meeting all requirements of the approved concept plan.
2. Installation of the landscaping in the areas of the site that will not be directly impacted by the construction of the dwelling units within 60 days after the completion of the installation of utilities and road construction for each phase of the project. All remaining landscaping is to be installed incrementally as each unit is completed or within 6 months of the issuance of the occupancy permit for each unit.
3. Establishment of a homeowners association for the purpose of assessing fees for the maintenance of the exterior of the dwellings, grounds, clubhouse, common areas and all other assets of the association.
4. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
5. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to the issuance of any grading permits for this project.
6. No commercial uses being proposed as part of this project as may be permitted with MPC approval in the RP-1 District. (See attached letter from the applicant's attorney).
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a Use on Review.