: First Baptist Church

6-D-13-DT

Approve As Requested

APPROVE Certificate 6-D-13-DT as submitted and shown on the attached plans.
Recommendation

Applicant Request
:
    • At the main entrance of the church, remove the bottom two limestone stair treeds and replace with concrete as shown in the attached plans. The concrete will be tinted to closely match the color and profile of the limestone stair treads.

Property Notes / Work to be Completed
    • First Baptist Church is listed on the National Register of Historic Places, however, staff has determined that it is not feasible to get replacement limestone to match the existing. These stair treads must be replaced because they hav cracked and are shifting. The new concrete stair treads will help stabilize the remaining limestone stair treads.

Meeting Date
June 7, 2013

First Baptist Church
510 W Main St

Applicant
Johnson & Galyon
Owner First Baptist Church

Staff
Mike Reynolds
Phone: 865-215-3827
Email: mike.reynolds@knoxplanning.org

Case History

Date Filed
June 7, 2013

Date Heard
June 7, 2013

Case History