Use On Review

6-H-21-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a church comprising approximately 12,340 square feet, subject to the following conditions.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
11012 Hardin Valley Rd.

South side of Hardin Valley Road, west side of Award Winning Way

Commission District 6


Size
20 acres

Sector
Northwest County

Land Use Designation? LDR (Low Density Residential) / HP (Hillside Protection)


Currently on the Property
Vacant land

Growth Plan
Planned Growth Area / Rural Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a church comprising approximately 12,340 square feet, subject to the following conditions.
1. Connection to sanitary sewer and meeting any other relevant requirements of the utility provider.
2. Installation of all landscaping as shown on development plan within six months of the issuance of an occupancy permit, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Installation of all sidewalks as identified on the concept plan. Sidewalks and crosswalks shall meet all applicable requirements of the Americans with Disabilities Act (ADA) and the Knox County Department of Engineering and Public Works.
4. Meeting all other applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements of the Knox County Zoning Ordinance.
6. Meeting all applicable requirements of the Knox County Fire Marshall?s office.
7. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Health.

With the conditions noted, this plan meets the requirements for a church in the PR/TO and OB/TO districts, which requires approval as a use on review.
Disposition Summary
APPROVE the development plan for a church comprising approximately 12,340 square feet, subject to the following conditions.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - July 10, 2021 - has passed.

The Process
Applicant

Valley Church UMC


Case History