Use On Review

6-P-01-UR

Recommended for approval
by the Planning Commission

APPROVE the plan for up 26 detached single family condominiums as shown subject to 12 conditions

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing system within Knox County (Ord. 91-1-102).
3. Installation of landscaping shown on the development plan within six months of the issuance of the occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Submission of a grading plan prior to commencing any grading of this site.
5. Reduce the pavement radius in the cul de sac bulb to 30' to lessen the amount of asphalt in the peripheral setback.
6. Grade back the bank at the intersection of S. Northshore and Hart road to improve sight distance to a




Sorey Construction
6-P-01-UR
Page 2


standard acceptable to the Knox County Dept. of Engineering and Public Works.
7. Provide a continuous Class A landscape screen (see attached) in the peripheral boundary setback behind units 21-23 along Hart Rd.
8. Maintaining 15' of undisturbed vegetation or provide a Class A landscape screen along the boundary between this project and the homes fronting on Nantasket Rd.
9. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
10. Meeting all applicable requirements of the Knox County Zoning Ordinance.
11. Installation of landscaping as shown on the revised development plant within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
12. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.

Applicant Request

+

Property Information

+
Location
East side of Hart Rd., north side of S. Northshore Dr.

Commission District 5


Size
7.43 acres

Sector
Southwest County

Currently on the Property
Vacant

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the plan for up 26 detached single family condominiums as shown subject to 12 conditions

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.

1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing system within Knox County (Ord. 91-1-102).
3. Installation of landscaping shown on the development plan within six months of the issuance of the occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Submission of a grading plan prior to commencing any grading of this site.
5. Reduce the pavement radius in the cul de sac bulb to 30' to lessen the amount of asphalt in the peripheral setback.
6. Grade back the bank at the intersection of S. Northshore and Hart road to improve sight distance to a




Sorey Construction
6-P-01-UR
Page 2


standard acceptable to the Knox County Dept. of Engineering and Public Works.
7. Provide a continuous Class A landscape screen (see attached) in the peripheral boundary setback behind units 21-23 along Hart Rd.
8. Maintaining 15' of undisturbed vegetation or provide a Class A landscape screen along the boundary between this project and the homes fronting on Nantasket Rd.
9. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
10. Meeting all applicable requirements of the Knox County Zoning Ordinance.
11. Installation of landscaping as shown on the revised development plant within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
12. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.
Disposition Summary
APPROVE the plan for up 26 detached single family condominiums as shown subject to 12 conditions

With the conditions noted, this plan meets the requirements for approval in the PR Zone and the other criteria for approval of a Use on Review.

Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing system within Knox County (Ord. 91-1-102).
3. Installation of landscaping shown on the development plan within six months of the issuance of the occupancy permits for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
4. Submission of a grading plan prior to commencing any grading of this site.
5. Reduce the pavement radius in the cul de sac bulb to 30' to lessen the amount of asphalt in the peripheral setback.
6. Grade back the bank at the intersection of S. Northshore and Hart road to improve sight distance to a




Sorey Construction
6-P-01-UR
Page 2


standard acceptable to the Knox County Dept. of Engineering and Public Works.
7. Provide a continuous Class A landscape screen (see attached) in the peripheral boundary setback behind units 21-23 along Hart Rd.
8. Maintaining 15' of undisturbed vegetation or provide a Class A landscape screen along the boundary between this project and the homes fronting on Nantasket Rd.
9. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
10. Meeting all applicable requirements of the Knox County Zoning Ordinance.
11. Installation of landscaping as shown on the revised development plant within six months of the issuance of the first occupancy permit for this project, or posting a bond with the Knox County Dept. of Engineering and Public Works to guarantee such installation.
12. A revised site plan reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - July 14, 2001 - has passed.

The Process
Applicant

Sorey Construction Co.


Case History