Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. (Modified by MPC) A flood insurance study per Federal Emergency Management Agency (FEMA) Publication #37 must be approved by Knox County Department of Engineering and Public Works prior to the County approving the design plan.
4. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for alteration of the blueline stream on the property.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationSoutheast side of Ball Rd., southwest of Johnson Rd.
Commission District 6
Size21.06 acres
Currently on the Property
Single-family residence and vacant land
Growth PlanUrban Growth Area (Outside City Limits)
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerKnoxville Utilities Board
TelephoneMetro Group Bell South Telephone
WaterKnoxville Utilities Board
Case Notes
−
+
Disposition Summary
APPROVE variances 1 - 6 because of topography, and the proposed variances will not create a traffic hazard
APPROVE the Concept Plan subject to 8 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. (Modified by MPC) A flood insurance study per Federal Emergency Management Agency (FEMA) Publication #37 must be approved by Knox County Department of Engineering and Public Works prior to the County approving the design plan.
4. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for alteration of the blueline stream on the property.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Staff Recommendation
APPROVE variances 1 - 6 because of topography, and the proposed variances will not create a traffic hazard
APPROVE the Concept Plan subject to 8 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. A flood insurance study per Federal Emergency Management Agency (FEMA) Publication #37 must be approved by FEMA prior to the Knox County Department of Engineering and Public Works approving the design plan.
4. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
5. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for alteration of the blueline stream on the property.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.