Development Plan

Planning Commission

9-F-23-DP

Approved

Approve the development plan for a beer brewery with an area of approximately 2,123 sq ft., subject to 7 conditions.

1) Installation of all landscaping as shown on the development plan within six months of the issuance of an occupancy permit or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) No uplighting shall be installed in accordance with TTCDA Guidelines.
3) Obtaining staff approval of revised landscaping plans that provide a landscape bed with ornamental trees and plantings at the entry to the site prior to the issuance of a COA, a condition of the TTCDA approval obtained on August 7, 2023.
4) Meeting all other applicable requirements of the TN Technology Corridor Development Authority (TTCDA).
5) Provision of a sidewalk connecting the facility through the site frontage.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knox County Zoning Ordinance.


Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
940 SANCTUARY LN

East side of Sanctuary Ln, north of Dutchtown Rd

Commission District 3


Size
8.08 acres

Place Type Designation
MU-SD (Mixed Use Special District)

Currently on the Property
Office

Growth Plan
Planned Growth Area

Case Notes

+
Disposition Summary
Approve the development plan for a beer brewery with an area of approximately 2,123 sq ft., subject to 7 conditions.

1) Installation of all landscaping as shown on the development plan within six months of the issuance of an occupancy permit or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) No uplighting shall be installed in accordance with TTCDA Guidelines.
3) Obtaining staff approval of revised landscaping plans that provide a landscape bed with ornamental trees and plantings at the entry to the site prior to the issuance of a COA, a condition of the TTCDA approval obtained on August 7, 2023.
4) Meeting all other applicable requirements of the TN Technology Corridor Development Authority (TTCDA).
5) Provision of a sidewalk connecting the facility through the site frontage.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knox County Zoning Ordinance.

Staff Recommendation
Approve the development plan for a beer brewery with an area of approximately 2,123 sq ft., subject to 7 conditions.

1) Installation of all landscaping as shown on the development plan within six months of the issuance of an occupancy permit or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
2) No uplighting shall be installed in accordance with TTCDA Guidelines.
3) Obtaining staff approval of revised landscaping plans that provide a landscape bed with ornamental trees and plantings at the entry to the site prior to the issuance of a COA, a condition of the TTCDA approval obtained on August 7, 2023.
4) Meeting all other applicable requirements of the TN Technology Corridor Development Authority (TTCDA).
5) Provision of a sidewalk connecting the facility through the site frontage.
6) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knox County Zoning Ordinance.
The applicant is seeking approval to construct a 2,123 sq. ft. brew pub with 36 seats (including internal and external) on an existing site shared with a church. The combined buildings are 5,148 sq. ft.

Per the Knox County Sidewalk Ordinance, a sidewalk will be required from the site through the frontage of the property line.

DEVELOPMENT PLAN ANALYSIS PER ARTICLE 6, SECTION 6.50.06 (APPROVAL OR DENIAL)
In the exercise of its administrative judgment, the Planning Commission shall determine if the proposed plan is in harmony with the general purpose and intent of the zoning ordinance and adopted plans.

1) ZONING ORDINANCE
A. The PC zones allows a general mix or retail and commercial uses that also include offices, commercial services and light distribution centers. A beer brewery is consistent with the PC zone's stated intent.
TO (Technology Overlay):
B. The TO zone requires approval by the Tennessee Technology Corridor Development Authority (TTCDA) and plans were approved in August 2023 (Case #7-B-23-TOB). One of the conditions was for a revised landscaping plan adding ornamental trees and plantings at the entry to the site be approved administratively by staff prior to the issuance of a COA. Upon meeting that condition, the proposed plans would be in accordance with TTCDA Guidelines.

2) GENERAL PLAN - DEVELOPMENT POLICIES
A. (Policy 8.3) Focus on design quality and neighborhood compatibility in reviewing development proposals. The proposed structure is compatible with the site and neighborhood. This development abuts a single family detached residential subdivision to the rear. The proposed building has a small footprint and deliveries would be made by smaller trucks or vans. The existing vegetation along the northeast property line shared with a single family residential neighborhood provides a visual buffer to the site. The proposed additional commercial building on an existing commercial site is not expected to have adverse impacts on the surrounding area.

3) NORTHWEST COUNTY SECTOR PLAN
A. The property is classified as MU-SD (Mixed Use-Special District, Dutchtown Road/Lovel Road). The scale of the commercial operation is consistent with other developments in the area.

What's next?

+
Planning Commission decisions on Development Plans (DP) are final unless appealed.

Appeals can be filed with the Knox County Board of Zoning Appeals (BZA) or a court of competent jurisdiction within 30 days of the Planning Commission's decision (Knox County, Tennessee Code of Ordinances, Appendix A, Zoning, 6.50.08).

Applicant

Jared Eisenhower


Case History