Use On Review

9-L-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a 15,000 square foot office building, subject to 8 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing the proposed landscaping as shown on the landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
5. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site for approval by the TTCDA.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the general standards for approval of a Use-on-Review.

Applicant Request

+

Property Information

+
Location
0 Castaic Ln

South of Hardin Valley Rd., south end of Castaic Ln., and west of Pellissippi Parkway

Commission District 6


Size
6.37 acres

Sector
Northwest County

Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for a 15,000 square foot office building, subject to 8 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing the proposed landscaping as shown on the landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
5. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site for approval by the TTCDA.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the general standards for approval of a Use-on-Review.
Disposition Summary
APPROVE the development plan for a 15,000 square foot office building, subject to 8 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installing the proposed landscaping as shown on the landscape plan, within six months of the issuance of occupancy permits for this project, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.
3. Obtaining a Certificate of Appropriateness from the Tennessee Technology Corridor Development Authority (TTCDA).
4. Obtaining approval of signage by TTCDA and MPC prior to any signs being placed on the site.
5. Submitting a lighting plan showing location of all proposed lighting and indicating no spillover of light or glare off-site for approval by the TTCDA.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Meeting all applicable requirements of the Knox County Zoning Ordinance.
8. Submitting a revised site plan to MPC for certification, reflecting the above conditions, prior to issuance of any building permits for this project.

With the conditions noted above, this request meets the requirements for approval in the PC zone, and the general standards for approval of a Use-on-Review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - October 13, 2001 - has passed.

The Process