Property Information
−
+
LocationNorth side of W. Governor John Sevier Hwy., east side of Maryville Pike
Commission District 9
Size11.16 acres
Currently on the Property
Vacant
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerKnox-Chapman Utility District
TelephoneMetro Group Bell South Telephone
WaterKnox-Chapman Utility District
Case Notes
−
+
Disposition Summary
APPROVE variances 1 & 2 because these variances were previously approved and the road construction is complete
APPROVE the Concept Plan subject to 7 conditions
Staff Recommendation
APPROVE variances 1 & 2 because these variances were previously approved and the road construction is complete
APPROVE the Concept Plan subject to 7 conditions
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Use on review approval of any proposed development prior to commencing any further grading on this site.
3. Place a note on the final plat that all lots with the exception of lot 12 and lot 1 of Unit one are to have access to the internal street system only. Lot 12 and lot 1 of Unit one may be permitted one shared access to point W. Governor John Sevier Highway as shown on the Concept Plan.
4. Each lot will have to observe a 50' peripheral setback unless a comprehensive development plan is presented through the use on review process for the entire site.
5. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Zoning Ordinance.
7. A final plat application based on this concept plan will not be accepted for review by MPC until certification of design plan approval has been submitted to MPC staff.