Subdivision

Concept Plan

9-SA-01-C

Recommended for approval
by the Planning Commission

APPROVE variances 1 & 2 because these variances were previously approved and the road construction is complete

APPROVE the Concept Plan subject to 7 conditions


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
Southwood Commercial Park
Lots
12 (Split)

Variances

1. Horizontal curve variance from 400' to 363.39' at sta. 3+50 of Circle Oak Dr.
2. Pavement corner radius from 75' to 25' at the intersection of Circle Oak Dr. and Martel Ln.


Property Information

+
Location
North side of W. Governor John Sevier Hwy., east side of Maryville Pike

Commission District 9


Size
11.16 acres

Sector
South County

Currently on the Property
Vacant

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE variances 1 & 2 because these variances were previously approved and the road construction is complete

APPROVE the Concept Plan subject to 7 conditions

1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
2. Use on review approval of any proposed development prior to commencing any further grading on this site.
3. Place a note on the final plat that all lots with the exception of lot 12 and lot 1 of Unit one are to have access to the internal street system only. Lot 12 and lot 1 of Unit one may be permitted one shared access to point W. Governor John Sevier Highway as shown on the Concept Plan.
4. Each lot will have to observe a 50' peripheral setback unless a comprehensive development plan is presented through the use on review process for the entire site.
5. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Zoning Ordinance.
7. A final plat application based on this concept plan will not be accepted for review by MPC until certification of design plan approval has been submitted to MPC staff.
Disposition Summary
APPROVE variances 1 & 2 because these variances were previously approved and the road construction is complete

APPROVE the Concept Plan subject to 7 conditions

What's next?

+
After the Planning CommissionAppeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

Southwood Commercial Park

J.W. Harb