Subdivision

Concept Plan

9-SC-23-C

Approved with conditions
by the Planning Commission

Approve the requested variance based on the justification provided by the applicant and recommendations of Knox County Department of Engineering and Public Works.

Approve the Concept Plan subject to 4 conditions.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
JW Construction on Brown Gap Road
Lots
11 (Split)
Proposed Density
4

Variances

VARIANCES
1. Reduce the minimum vertical curve on Road A from K=25 to K=15 at PVI STA 1+00

ALTERNATIVE DESIGN STANDARDS REQUIRING KNOXVILLE-KNOX COUNTY PLANNING COMMISSION APPROVAL
1. None

ALTERNATIVE DESIGN STANDARDS REQUIRING KNOX COUNTY ENGINEERING AND PUBLIC WORKS APPROVAL
** See attached variance and alternative design request form


Property Information

+
Location
5711 BROWN GAP RD

Southwest side of Brown Gap Rd, southeast of E Emory Rd

Commission District 7


Size
2.74 acres

Sector
North County

Land Use Designation? LDR (Low Density Residential)


Currently on the Property
Agriculture/Forestry/Vacant Land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
Approve the requested variance based on the justification provided by the applicant and recommendations of Knox County Department of Engineering and Public Works.

Approve the Concept Plan subject to 4 conditions.

1) Connection to sanitary sewer and meeting other relevant utility provider requirements.
2) Provision of street name consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4) Establishing a property owners association or other legal entity responsible for maintaining common facilities before certification of the final plat for the subdivision,
Disposition Summary
Approve the requested variance based on the justification provided by the applicant and recommendations of Knox County Department of Engineering and Public Works.

Approve the Concept Plan subject to 4 conditions.

What's next?

+
After the Planning CommissionAppeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

JW Construction on Brown Gap Road

JW Construction


Case History