Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2.. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4.. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Certification on the final plat by the applicant's surveyor that there is 300' feet of sight distance in both directions along Crippen Rd.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. Include the required Minimum Floor Elevation (MFE) for lots 13, 14, & 15 on the final plat.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationNorth side of Crippen Rd., east of Winter Oaks Way
Commission District 7
Size6 acres
Currently on the Property
Vacant
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerHallsdale-Powell Utility District
TelephoneTDS Telecom - Halls
WaterHallsdale-Powell Utility District
Case Notes
−
+
Disposition Summary
APPROVE variances 1 & 2 because the site's topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard
APPROVE the Concept Plan subject to 9 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2.. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4.. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Certification on the final plat by the applicant's surveyor that there is 300' feet of sight distance in both directions along Crippen Rd.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. Include the required Minimum Floor Elevation (MFE) for lots 13, 14, & 15 on the final plat.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Staff Recommendation
APPROVE variances 1 & 2 because the site's topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard
APPROVE the Concept Plan subject to 9 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2.. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4.. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation.
5. Certification on the final plat by the applicant's surveyor that there is 300' feet of sight distance in both directions along Crippen Rd.
6. Place a note on the final plat that all lots will have access only to the internal street system.
7. Meeting all requirements of the approved use on review development plan.
8. Include the required Minimum Floor Elevation (MFE) for lots 13, 14, & 15 on the final plat.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.