Use On Review

1-K-15-UR

Recommended for approval
by the Planning Commission

APPROVE the request for the proposed cathedral and associated site improvements as shown on the development plan, subject to 9 conditions.


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Property Information

+
Location
805 S Northshore Dr

Southwest side of S. Northshore Dr., south of Erin Dr.

Council District 2
Census Tract 44.04


Size
16.50 acres

Sector
West City

Land Use Designation? O & BP-1


Currently on the Property
Church and related facilities

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the request for the proposed cathedral and associated site improvements as shown on the development plan, subject to 9 conditions.
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Installation of signage for the new access drive on Erin Dr. that clearly identifies left turn restrictions at that location, subject to approval by the Knoxville Department of Engineering.
3. Implementing the recommendations from the Traffic Impact Study prepared by Cannon & Cannon Inc., and dated December 23, 2014 (See attachment).
4. Installation of the sidewalks and pedestrian crossings as identified on the development plan.
5. Meeting all applicable requirements of the Knoxville Department of Engineering.
6. Approval of a final plat that combines the property into a single lot.
7. Installation of landscaping as shown on the development plan within six months of the issuance of an occupancy permit for this project.
8. All lighting shall be directed away from the adjoining properties and streets.
9. Meeting all applicable requirements of the Knoxville Zoning Ordinances.

With the conditions noted above, this request meets the requirements for approval in the R-1, O-1 and C-6 zoning districts and other criteria for a use-on-review.
Disposition Summary
APPROVE the request for the proposed cathedral and associated site improvements as shown on the development plan, subject to 9 conditions.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - January 23, 2015 - has passed.

The Process
Applicant

Sacred Heart Cathedral


Case History