Subdivision

Final Plat

1-SE-24-F

Approved

The concept plan indicating the overall layout and design for this plat was approved on 5/13/2021 as Planning Case 5-SB-21-C. Per Subdivision Regulations, Sections 2.08.A and 2.10.F, the final plat must be in substantial conformance with the approved co


Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
Final Plat of Catatoga Subdivision Phase 1
Lots
42 (Split)
Residential?
Yes - MF

Property Information

+
Location
1737 N. Campbell Station Rd.

West side of Campbell Station Road and North of Yarnell Road

Commission District 6


Size
23.84 acres


Growth Plan
Rural Area

What's next?

+
Final Plat appeals will be heard by the Planning Commission.
Appeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

Final Plat of Catatoga Subdivision Phase 1

Ryan Lynch


Case History