Details of Action
−
+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Revising the landscape plan to include evergreen screening between the fence and the southern property line (along the lots that front on Murray Dr.) and submitting the revised plan to MPC Staff for approval.
3. (Added by Planning Commission 11/10/05) Revising the landscape plan to include evergreen screening between the fence and the northern property line (Joint Permanent Easement) and submitting the revised plan to MPC Staff for approval.
4. During the clearing and construction phase of the development, providing protection barriers around the area identified on the landscape plan as "undisturbed natural buffer".
5. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of building permits, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
6. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
7. Any outdoor storage area meeting the requirements of the CA District.
8. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
9. Meeting all applicable requirements of the Knox County Health Department.
With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.
Property Information
−
+
Location6175 Primus Rd
Southwest side of Primus Rd., north of Murray Dr.
Commission District 6
Size3.40 acres
SectorLand Use Designation? LDR
Currently on the Property
Telecommunications tower, billboard and vacant land
Growth PlanUrban Growth Area (Outside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a self-service storage facility with a total building area of 43,440 square feet in the CA zone, subject to 8 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Revising the landscape plan to include evergreen screening between the fence and the southern property line (along the lots that front on Murray Dr.) and submitting the revised plan to MPC Staff for approval.
3. During the clearing and construction phase of the development, providing protection barriers around the area identified on the landscape plan as "undisturbed natural buffer".
4. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of building permits, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
6. Any outdoor storage area meeting the requirements of the CA District.
7. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
8. Meeting all applicable requirements of the Knox County Health Department.
With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a self-service storage facility with a total building area of 43,440 square feet in the CA zone, subject to 9 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Revising the landscape plan to include evergreen screening between the fence and the southern property line (along the lots that front on Murray Dr.) and submitting the revised plan to MPC Staff for approval.
3. (Added by Planning Commission 11/10/05) Revising the landscape plan to include evergreen screening between the fence and the northern property line (Joint Permanent Easement) and submitting the revised plan to MPC Staff for approval.
4. During the clearing and construction phase of the development, providing protection barriers around the area identified on the landscape plan as "undisturbed natural buffer".
5. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of building permits, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
6. All outdoor lighting shall be shielded to direct light and glare away from all adjoining property.
7. Any outdoor storage area meeting the requirements of the CA District.
8. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
9. Meeting all applicable requirements of the Knox County Health Department.
With the conditions noted above, this request meets all requirements for approval in the CA zone, as well as other criteria for approval of a use on review.