APPROVE the request to permit the construction of one detached dwelling on each lot as shown on the plan for up to 55 detached dwellings in Greenbrook and 70 detached dwellings in Teal Creek subject to 1 condition


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval in the PR (Planned Residential) zone and the other criteria for approval of a concept plan and use on review.

Applicant Request

+

Property Information

+
Location
Northeast side of Solway Rd., north of Gable Run Dr.

Commission District 6


Size
35.33 acres

Sector
Northwest County

Land Use Designation? LDR (Low Density Residential)


Currently on the Property
Vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the request to permit the construction of one detached dwelling on each lot as shown on the plan for up to 55 detached dwellings in Greenbrook and 70 detached dwellings in Teal Creek subject to 1 condition
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval in the PR (Planned Residential) zone and the other criteria for approval of a concept plan and use on review.
Disposition Summary
APPROVE the request to permit the construction of one detached dwelling on each lot as shown on the plan for up to 55 detached dwellings in Greenbrook and 70 detached dwellings in Teal Creek subject to 1 condition
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.

With the conditions noted, this plan meets the requirements for approval in the PR (Planned Residential) zone and the other criteria for approval of a concept plan and use on review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - December 10, 2010 - has passed.