Subdivision

Concept Plan

11-SB-05-C

Recommended for approval
by the Planning Commission

APPROVE the Concept Plan subject to 9 conditions


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Approval of the rezoning of this site to PR (Planned Residential) at a density of 3.3 du/ac or greater.
5. Dedication of the required 44' from the centerline of S. Northshore Dr. and 25' from the centerline of Harvey Rd.
6. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the drainage system and any common area.
7. Placing a note on the final plat that all lots will have access from the internal road system only.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.

Applicant Request

+
Subdivision
Arbor Gate Subdivision Revised
Lots
48 (Split)
Proposed Density
3.33 du/ac
Residential?
Yes

Variances

None


Property Information

+
Location
East side of Harvey Rd., south of S. Northshore Dr.

Commission District 5


Size
14.47 acres

Sector
Southwest County

Currently on the Property
Two single family dwellings and vacant land

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the Concept Plan subject to 9 conditions
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Approval of the rezoning of this site to PR (Planned Residential) at a density of 3.3 du/ac or greater.
5. Dedication of the required 44' from the centerline of S. Northshore Dr. and 25' from the centerline of Harvey Rd.
6. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the drainage system and any common area.
7. Placing a note on the final plat that all lots will have access from the internal road system only.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Disposition Summary
APPROVE the Concept Plan subject to 9 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Approval of the rezoning of this site to PR (Planned Residential) at a density of 3.3 du/ac or greater.
5. Dedication of the required 44' from the centerline of S. Northshore Dr. and 25' from the centerline of Harvey Rd.
6. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the drainage system and any common area.
7. Placing a note on the final plat that all lots will have access from the internal road system only.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.

What's next?

+
After the Planning CommissionAppeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

Arbor Gate Subdivision Revised

North American Development Corporation


Case History