Row Closure

2-B-02-SC


by the Planning Commission


See case notes below

Request

Property Info

Case Notes

What's next?

Applicant Request

+

Right-of-way is being incorporated into Phase II of Caswell Park

Close Street From
North side E. Fifth Ave.
To
First Creek
Reason for Closure
Right-of-way is being incorporated into Phase II of Caswell Park
Objections

KUB has requested several required easements. (See attached letter.)


Property Information

+
Location
0 Jessamine Street

Council District 6


Sector
Central City

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE, subject to any required easements, including the following requested by KUB:
1) 50' wide electric line easement,
2) 30' wide wastewater line easement,
3) 15' wide water line easement, and
4) 15' wide gas line easement.

This right-of-way will be incorporated into the adjacent developing city park.

What's next?

+
After the Planning Commission
  • Appeal to Because of its location in the City, appeals will be heard by Knoxville City Council
  • Appeal by The appeal deadline has passed
The Process
Applicant

City of Knoxville


Case History