Details of Action
−
+
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Revising the grading and drainage plan and landscape plan to reflect the changes made to the revised site plan.
6. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for any proposed development on the lots.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the approved concept plan.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan in the PC District and the other criteria for approval of a Use-on-Review.
Property Information
−
+
LocationSouth side of Hardin Valley Rd., southwest of Cherahala Bv.
Commission District 6
Size1.61 acres
SectorLand Use Designation? C (Commercial) & SLPA (Slope Protection)
Currently on the Property
Vacant land
Growth PlanPlanned Growth Area
- Utilities
SewerWest Knox Utility District
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a 4,890 square foot bank in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, subject to 6 conditions:
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Revising the grading and drainage plan and landscape plan to reflect the changes made to the revised site plan.
6. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for any proposed development on the lots.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the approved concept plan.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan in the PC District and the other criteria for approval of a Use-on-Review.
Disposition Summary
APPROVE the development plan for a 4,890 square foot bank in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, subject to 6 conditions:
Details of Action
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
5. Revising the grading and drainage plan and landscape plan to reflect the changes made to the revised site plan.
6. Installing all landscaping, as shown on the revised landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for any proposed development on the lots.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Meeting all applicable requirements of the approved concept plan.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan in the PC District and the other criteria for approval of a Use-on-Review.