Details of Action
−
+
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the City of Knoxville Department of Engineering.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six month of issuance of occupancy permits for each phase of the project.
5. Meeting all requirements of the City of Knoxville Urban Forester.
6. The two access points from Piney Grove Church Rd. must be gated at all times except for periods when church services are taking place.
7. Meeting all applicable requirements of the previously approved development plan for the church expansion (11-C-01-UR).
Property Information
−
+
Location7635 Middlebrook Pike
North side of Middlebrook Pike, south side of Piney Grove Church Rd., and west side of Adell Ree Park Ln.
Council District 3
Census Tract 46.14
Size15.90 acres
Planning SectorNorthwest County
Land Use Classification Low Density Residential Low Density Residential
Currently on the Property
Public / Quasi Public Land
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Disposition Summary
APPROVE the request for a church parking lot expansion in the R-1 zone, subject to 7 conditions.
Details of Action
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the City of Knoxville Department of Engineering.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six month of issuance of occupancy permits for each phase of the project.
5. Meeting all requirements of the City of Knoxville Urban Forester.
6. The two access points from Piney Grove Church Rd. must be gated at all times except for periods when church services are taking place.
7. Meeting all applicable requirements of the previously approved development plan for the church expansion (11-C-01-UR).
Staff Recommendation
APPROVE the request for a church parking lot expansion in the R-1 zone, subject to 7 conditions.
1. Meeting all applicable requirements of the City of Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the City of Knoxville Department of Engineering.
3. Meeting all requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the development plan, within six month of issuance of occupancy permits for each phase of the project.
5. Meeting all requirements of the City of Knoxville Urban Forester.
6. The two access points from Piney Grove Church Rd. must be gated at all times except for periods when church services are taking place.
7. Meeting all applicable requirements of the previously approved development plan for the church expansion (11-C-01-UR).
With the conditions noted above, this request meets all the requirements for approval in the R-1 zone, as well as other criteria for use on review approval.