Property Information
−
+
LocationNortheast side of Schaeffer Rd., north of Lovell Rd.
Commission District 6
Size23.34 acres
Sector
Currently on the Property
Vacant land and office building under construction
Growth PlanPlanned Growth Area
- Utilities
ElectricityLenoir City Utility District
Natuarl GasKnoxville Utilities Board
SewerWest Knox Utility District
TelephoneMetro Group Bell South Telephone
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE variances 1 and 2 because the site's location and topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 11 conditions:
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Providing a 50' corner radius for the edge of pavement and right-of-way at the intersection of Center Ridge Ln. and Schaeffer Rd.
4. Providing two exiting lanes from Center Ridge Ln. onto Schaeffer Rd. subject to final approval by Knox County Department of Engineering and Public Works.
5. Final design of the access drives off of Center Ridge Ln. subject to approval by Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for alteration of the blueline stream.
8. Certification on the final plat by the applicant's surveyor that there is 300 feet of sight distance in both directions along Schaeffer Rd.
9. Place a note on the final plat that all lots will have access only to the internal street system.
10. Meeting all requirements of the approved use on review development plan (File number 7-Q-04-UR).
11. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
With the conditions noted, this plan meets the requirements for approval of a Concept Plan in the BP/TO and OB/TO Zones.
Disposition Summary
APPROVE variances 1 and 2 because the site's location and topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard.
APPROVE the Concept Plan subject to 11 conditions: