Details of Action
−
+
1. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the Knoxville City Engineer.
3. Meeting all applicable requirements of the Knoxville City Arborist.
4. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
5. Installation of landscaping, including the tree buffer, as shown on the development plan within six months of the issuance of the first occupancy permit for this project.
6. Obtaining a street connection permit from the Tenn. Dept. of Transportation.
7. Construction of the proposed easement being completed prior to obtaining any certificates of occupancy.
8. (Amended by MPC 5/12/05) A physical barrier to consist of landscaping being installed on applicant's property to block acccess to Eastburn Dr. prior to commencing construction of these facilities.
9. Prior to commencing any grading on this project, review and approval of a subdivision plat by MPC separating the 6.3 acre assisted living site from the remainder of the church campus. This plat will also establish a 40' wide joint permanent easement, designed to City standards, across the church property and note that all access will be via the proposed easement to Asheville Hwy..
10. A revised site plan must be submitted to MPC staff prior to issuance of any building or grading permits.
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a use on review.
Property Information
−
+
Location4615 Asheville Hwy
North side Asheville Hwy., east of Macedonia Ln.
Council District 6
Census Tract 32
Size6.30 acres
SectorLand Use Designation? Medium Density Residential
Currently on the Property
Church, school & day care
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
SewerKnoxville Utilities Board
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the request for 54 assisted living units and 29 independent living apartments at this location as shown on the development plan subject to 10 conditions
1. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the Knoxville City Engineer.
3. Meeting all applicable requirements of the Knoxville City Arborist.
4. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
5. Installation of landscaping, including the tree buffer, as shown on the development plan within six months of the issuance of the first occupancy permit for this project.
6. Obtaining a street connection permit from the Tenn. Dept. of Transportation.
7. Construction of the proposed easement being completed prior to obtaining any certificates of occupancy.
8. A physical barrier to consist of a combination of fencing and landscaping being installed at the existing dead-end of Eastburn Dr. prior to commencing construction of these facilities.
9. Prior to commencing any grading on this project, review and approval of a subdivision plat by MPC separating the 6.3 acre assisted living site from the remainder of the church campus. This plat will also establish a 40' wide joint permanent easement, designed to City standards, across the church property and note that all access will be via the proposed easement to Asheville Hwy..
10. A revised site plan must be submitted to MPC staff prior to issuance of any building or grading permits.
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a use on review.
Disposition Summary
APPROVE the request for 54 assisted living units and 29 independent living apartments at this location as shown on the development plan subject to 10 conditions
Details of Action
1. Meeting all applicable requirements of the Knoxville Zoning Ordinance.
2. Meeting all applicable requirements of the Knoxville City Engineer.
3. Meeting all applicable requirements of the Knoxville City Arborist.
4. Connection to sanitary sewer and meeting any other relevant requirement of the Knox County Health Dept.
5. Installation of landscaping, including the tree buffer, as shown on the development plan within six months of the issuance of the first occupancy permit for this project.
6. Obtaining a street connection permit from the Tenn. Dept. of Transportation.
7. Construction of the proposed easement being completed prior to obtaining any certificates of occupancy.
8. (Amended by MPC 5/12/05) A physical barrier to consist of landscaping being installed on applicant's property to block acccess to Eastburn Dr. prior to commencing construction of these facilities.
9. Prior to commencing any grading on this project, review and approval of a subdivision plat by MPC separating the 6.3 acre assisted living site from the remainder of the church campus. This plat will also establish a 40' wide joint permanent easement, designed to City standards, across the church property and note that all access will be via the proposed easement to Asheville Hwy..
10. A revised site plan must be submitted to MPC staff prior to issuance of any building or grading permits.
With the conditions noted, this plan meets the requirements for approval in the RP-1 District and the other criteria for approval of a use on review.