Use On Review

5-G-05-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a convenience store with gasoline pumps in the CN (Neighborhood Commercial) zoning district, subject to 5 conditions:


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the revised (6/7/05) landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Installing a traffic signal in the south direction to serve traffic entering and exiting the proposed development, per requirements of the Knox County Department of Engineering and Public Works.

Applicant Request

+

Property Information

+
Location
5904 Washington Pike

Southeast side Washington Pike, southeast of Murphy Rd.

Commission District 8
Census Tract 52.01


Size
1.40 acres

Sector
Northeast County

Land Use Designation? Neighborhood Commercial


Currently on the Property
Vacant land

Growth Plan
Urban Growth Area (Outside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the development plan for a convenience store with gasoline pumps in the CN (Neighborhood Commercial) zoning district, subject to 5 conditions:
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the revised (6/7/05) landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Installing a traffic signal in the south direction to serve traffic entering and exiting the proposed development, per requirements of the Knox County Department of Engineering and Public Works.

With the conditions noted above and with the approved BZA variances, this request meets the requirements for approval in the CN zone, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a convenience store with gasoline pumps in the CN (Neighborhood Commercial) zoning district, subject to 5 conditions:
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
3. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
4. Installing all landscaping, as shown on the revised (6/7/05) landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
5. Installing a traffic signal in the south direction to serve traffic entering and exiting the proposed development, per requirements of the Knox County Department of Engineering and Public Works.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - July 9, 2005 - has passed.

The Process
Applicant

Paul Anastasio - Michael Brady, Inc.


Case History