Use On Review

6-R-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for a monopole telecommunications tower subject to 8 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1) Obtaining FAA approval for construction of the tower.
2) Use of a dual lighting system for the structure if approved by FAA.
3) That the height of the tower not exceed 170'.
4) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational.
5) Meeting all applicable requirements of the Knoxville Zoning Ordinance.
6) Meeting all applicable requirements of the Knoxville Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knoxville City Arborist.
8) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.

With the conditions noted, the request meets all requirements for approval of a use-on-review.

Applicant Request

+

Property Information

+
Location
0 Town View Dr

South side of Town View Dr., across from Green Elementary School.

Council District 6


Size
1.92 acres

Sector
Central City

Currently on the Property
Vacant land

Growth Plan
Urban Growth Area (Inside City Limits)

Case Notes

+
Staff Recommendation
APPROVE the development plan for a monopole telecommunications tower subject to 8 conditions.
1) Obtaining FAA approval for construction of the tower.
2) Use of a dual lighting system for the structure if approved by FAA.
3) That the height of the tower not exceed 170'.
4) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational.
5) Meeting all applicable requirements of the Knoxville Zoning Ordinance.
6) Meeting all applicable requirements of the Knoxville Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knoxville City Arborist.
8) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.

With the conditions noted, the request meets all requirements for approval of a use-on-review.
Disposition Summary
APPROVE the development plan for a monopole telecommunications tower subject to 8 conditions.
Details of Action
1) Obtaining FAA approval for construction of the tower.
2) Use of a dual lighting system for the structure if approved by FAA.
3) That the height of the tower not exceed 170'.
4) Installing proposed landscaping as shown on the site plan within six months of the tower becoming operational.
5) Meeting all applicable requirements of the Knoxville Zoning Ordinance.
6) Meeting all applicable requirements of the Knoxville Department of Engineering and Public Works.
7) Meeting all applicable requirements of the Knoxville City Arborist.
8) A revised site plan, reflecting the conditions of approval must be submitted to MPC staff prior to issuance of any building permits for the project.

With the conditions noted, the request meets all requirements for approval of a use-on-review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - July 27, 2001 - has passed.

The Process
Applicant

National Wireless Construction, LLC


Case History