Details of Action
−
+
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for crossing the blueline stream.
5. Placing a note on the final plat that all lots will have access only to the internal street system.
6. Approval of Lot 1 is conditioned on the applicant documenting that there is an adequate building site on the lot.
7. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the common area and drainage facilities.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationWest side of Tipton Station Rd., south of Chapman Hwy.
Commission District 9
Size35.59 acres
Sector
Currently on the Property
Residence and vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerKnox-Chapman Utility District
TelephoneMetro Group Bell South Telephone
WaterKnox-Chapman Utility District
Case Notes
−
+
Staff Recommendation
APPROVE variances 1-8 because the site's topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard
APPROVE the concept plan subject to 9 conditions
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for crossing the blueline stream.
5. Placing a note on the final plat that all lots will have access only to the internal street system.
6. Approval of Lot 1 is conditioned on the applicant documenting that there is an adequate building site on the lot.
7. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the common area and drainage facilities.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Disposition Summary
APPROVE variances 1-8 because the site's topography restricts compliance with the Subdivision Regulations, and the proposed variances will not create a traffic hazard
APPROVE the concept plan subject to 9 conditions
Details of Action
1. Connection to sanitary sewer and meeting any other relevant requirements of the Knox County Health Department.
2. Provision of street names which are consistent with the Uniform Street Naming and Addressing System within Knox County (County Ord. 91-1-102).
3. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
4. Meeting all applicable requirements and obtaining all required permits from the Tennessee Department of Environment and Conservation for crossing the blueline stream.
5. Placing a note on the final plat that all lots will have access only to the internal street system.
6. Approval of Lot 1 is conditioned on the applicant documenting that there is an adequate building site on the lot.
7. Prior to certification of the final plat for the subdivision, establishing a property owners association that will be responsible for maintenance of the common area and drainage facilities.
8. Meeting all requirements of the approved use on review development plan.
9. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.