Request

Property Info

Case Notes

What's next?

Applicant Request

+
Subdivision
Lantern Park
Lots
7 (Split)
Proposed Density
2.82 du/ac
Residential?
Yes - SF

Variances

None


Property Information

+
Location
0 Mission Hill Ln.

West side of Mission Hills Ln, north side of Hardin Valley Rd

Commission District 6


Size
2.90 acres

Sector
Northwest County

Land Use Designation? RR (Rural Residential), HP (Hillside Protection), SP (Stream Protection)


Currently on the Property
Agriculture/Forestry/Vacant Land

Growth Plan
Rural Area

Case Notes

+
Staff Recommendation
Approve the Concept Plan subject to 9 conditions.
1) Connection to sanitary sewer and meeting other relevant utility provider requirements.
2) The centralized mail kiosk for the Lantern Park Subdivision must be located along Lantern Park Lane, subject to the United States Postal Service (USPS) approving the new location. The kiosk must be moved prior to the certification of a final plat for lots in Phase 2. If the USPS denies relocation of the kiosk, documentation of the denial must be provided to Knox County Engineering and Public Works before certification.
3) Providing an access easement for the sidewalk through Lot 27 and OS-3 per the requirements of Knox County Engineering and Public Works during the design plan phase.
4) Providing a minimum 30 ft greenway easement on the south side of Connor Creek per the requirements of Knox County Parks and Recreation and Knox County Engineering and Public Works during the design plan phase.
5) Meeting all applicable requirements of the Knox County Zoning Ordinance, including but not limited to the intersection spacing requirements of Article 3, Section 3.51.02.C. of the Knox County Zoning Ordinance.
6) Providing a sidewalk along the Mission Hill Lane frontage per the requirements of the Knox County Sidewalk Ordinance.
7) Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
8) Renumbering the lots on the Final Plat for Phase 2 so as not to skip lot numbers and as otherwise required per Article 2.10.F.9.
9) Before certification of the final plat for the subdivision, establish a property owners association or other legal entity responsible for maintaining common facilities, such as common areas, amenities, private roads, and/or stormwater drainage systems.
Disposition Summary
Approve the Concept Plan subject to 9 conditions.

What's next?

+
After the Planning CommissionAppeals of Concept Plans and Final Plats are filed with Chancery CourtThe Process
Applicant

Lantern Park

Ryan Lynch


Case History