Details of Action
−
+
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Health Dept.
4. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
5. No land disturbance beyond the previously permitted demolition landfill borders until approval of the remediation plan for the Old City Landfill by Tenn. Dept. of Environment and Conservation.
6. No landfilling on top of the Old City Landfill until the approved remediation plan has been implemented.
7. No landfilling beyond the previously permitted demolition landfill borders until the buffer area along the eastern boundary has been legally created through the recording of the appropriate documents at the Knox County Register Deeds.
8. The landfill will be specifically limited to the area depicted on the site plan prepared by Environmental Systems Corporation, dated 7/8/2003.
9. Within one year of the closure of the landfill, a survey will be recorded that specifically defines the area of the site that has been landfilled.
10. Prior to commencing landfilling over the Old City Landfill provide MPC staff with evidence that the required bond has been posted with the State of Tennessee.
With the conditions noted, this plan meets the requirements for approval in the I (Industrial) and A (Agricultural) and the other criteria for approval of a use on review.
Property Information
−
+
LocationSouth of Old Rutledge Pk., west of Ellistown Rd.
Commission District 8
Size64.30 acres
Currently on the Property
Landfill
Growth PlanUrban Growth Area
- Utilities
SewerNortheast Knox Utility District
WaterNortheast Knox Utility District
Case Notes
−
+
Disposition Summary
APPROVE the request to expand the existing Poplar View Demolition Landfill as permitted in Article 4, Section 4.80 of the Knox County Zoning Ordinance as shown on the development plan subject to 10 conditions
Details of Action
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Health Dept.
4. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
5. No land disturbance beyond the previously permitted demolition landfill borders until approval of the remediation plan for the Old City Landfill by Tenn. Dept. of Environment and Conservation.
6. No landfilling on top of the Old City Landfill until the approved remediation plan has been implemented.
7. No landfilling beyond the previously permitted demolition landfill borders until the buffer area along the eastern boundary has been legally created through the recording of the appropriate documents at the Knox County Register Deeds.
8. The landfill will be specifically limited to the area depicted on the site plan prepared by Environmental Systems Corporation, dated 7/8/2003.
9. Within one year of the closure of the landfill, a survey will be recorded that specifically defines the area of the site that has been landfilled.
10. Prior to commencing landfilling over the Old City Landfill provide MPC staff with evidence that the required bond has been posted with the State of Tennessee.
With the conditions noted, this plan meets the requirements for approval in the I (Industrial) and A (Agricultural) and the other criteria for approval of a use on review.
Staff Recommendation
APPROVE the request to expand the existing Poplar View Demolition Landfill as permitted in Article 4, Section 4.80 of the Knox County Zoning Ordinance as shown on the development plan subject to 10 conditions
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Meeting all applicable requirements of the Knox County Dept. of Engineering and Public Works.
3. Meeting all applicable requirements of the Knox County Health Dept.
4. Meeting all applicable requirements and obtaining all required permits from the Tenn. Dept. of Environment and Conservation.
5. No land disturbance beyond the previously permitted demolition landfill borders until approval of the remediation plan for the Old City Landfill by Tenn. Dept. of Environment and Conservation.
6. No landfilling on top of the Old City Landfill until the approved remediation plan has been implemented.
7. No landfilling beyond the previously permitted demolition landfill borders until the buffer area along the eastern boundary has been legally created through the recording of the appropriate documents at the Knox County Register Deeds.
8. The landfill will be specifically limited to the area depicted on the site plan prepared by Environmental Systems Corporation, dated 7/8/2003.
9. Within one year of the closure of the landfill, a survey will be recorded that specifically defines the area of the site that has been landfilled.
10. Prior to commencing landfilling over the Old City Landfill provide MPC staff with evidence that the required bond has been posted with the State of Tennessee.
With the conditions noted, this plan meets the requirements for approval in the I (Industrial) and A (Agricultural) and the other criteria for approval of a use on review.