Details of Action
−
+
1. During the design plan stage of the project, addressing the timing of the construction and replatting necessary for this road project, subject to the approval City Engineering and MPC Staff.
2. During the design plan stage of the project, addressing how the remaining portions of the two lots at the intersection of Pinehurst Dr. will be resubdivided, subject to the approval City Engineering and MPC Staff.
3. Meeting all applicable requirements of the Knoxville Department of Engineering.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Property Information
−
+
LocationWashington Pike just south of Centerline Dr.
Council District 4
Size11.75 acres
Sector
Currently on the Property
Public street
Growth PlanUrban Growth Area (Inside City Limits)
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerKnoxville Utilities Board
TelephoneMetro Group Bell South Telephone
WaterKnoxville Utilities Board
Case Notes
−
+
Staff Recommendation
APPROVE the Concept Plan subject to 4 conditions
1. During the design plan stage of the project, addressing the timing of the construction and replatting necessary for this road project, subject to the approval City Engineering and MPC Staff.
2. During the design plan stage of the project, addressing how the remaining portions of the two lots at the intersection of Pinehurst Dr. will be resubdivided, subject to the approval City Engineering and MPC Staff.
3. Meeting all applicable requirements of the Knoxville Department of Engineering.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.
Disposition Summary
APPROVE the Concept Plan subject to 4 conditions
Details of Action
1. During the design plan stage of the project, addressing the timing of the construction and replatting necessary for this road project, subject to the approval City Engineering and MPC Staff.
2. During the design plan stage of the project, addressing how the remaining portions of the two lots at the intersection of Pinehurst Dr. will be resubdivided, subject to the approval City Engineering and MPC Staff.
3. Meeting all applicable requirements of the Knoxville Department of Engineering.
4. A final plat application based on this concept plan will not be accepted for review by the MPC until certification of design plan approval has been submitted to the MPC staff.