Use On Review

8-E-01-UR

Recommended for approval
by the Planning Commission

APPROVE the development plan for up to 29 attached single-family dwellings on individual lots subject to 3 conditions.


See case notes below

Details

Request

Property Info

Case Notes

What's next?

Details of Action

+
1. Meeting all applicable requirements of the approved concept subdivision plan.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Installation of landscaping shown on the landscape plan within six months of the issuance of the occupancy permits for this development, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review.

Applicant Request

+

Property Information

+
Location
1422 Choto Rd.

Northeast side of Choto Rd., north of Bruce Smith Rd.

Commission District 5


Size
10.70 acres

Sector
Southwest County

Growth Plan
Planned Growth Area

Case Notes

+
Staff Recommendation
APPROVE the development plan for up to 29 attached single-family dwellings on individual lots subject to 3 conditions.
1. Meeting all applicable requirements of the approved concept subdivision plan.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Installation of landscaping shown on the landscape plan within six months of the issuance of the occupancy permits for this development, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review.
Disposition Summary
APPROVE the development plan for up to 29 attached single-family dwellings on individual lots subject to 3 conditions.
Details of Action
1. Meeting all applicable requirements of the approved concept subdivision plan.
2. Meeting all applicable requirements of the Knox County Zoning Ordinance.
3. Installation of landscaping shown on the landscape plan within six months of the issuance of the occupancy permits for this development, or posting a bond with the Knox County Department of Engineering and Public Works to guarantee such installation.

With the conditions noted, this plan meets the requirements for approval of a Concept Plan and a Use-on-Review.

What's next?

+
As a Use On Review case, the Planning Commission's decision is final, and it will not be heard by a legislative body unless it is appealed.

The appeal deadline - October 13, 2001 - has passed.

The Process
Applicant

Jeffrey Fields


Case History