Details of Action
−
+
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Obtaining a variance from the Knox County Board of Zoning Appeals for a reduction in the number of required on-site parking spaces.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.
4. Obtaining approval for the resubdivision of the property.
5. A building permit being shall not be issued for this development until : a) Iron Gate Blvd. is constructed to a standard acceptable to the Knox County Department of Engineering and Public Works and opened for public use; b) the main driveway for Hardin Valley Crown Center Subdivision that borders this parcel on the north side is completed from Iron Gate Blvd. to the existing access easement/driveway located between the Bread Box Food Store and Bank East; and c) the improvements recommended in the Traffic Impact Study (Cannon & Cannon, Inc., dated 2/16/06) for the existing access easement out to Hardin Valley Rd., between the Bread Box Food Store and Bank East, have been constructed and approved by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
8. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.
Property Information
−
+
Location0 Iron Gate Blvd
Southwest side of Iron Gate Blvd., southeast of Hardin Valley Rd.
Commission District 6
Census Tract 59.01
Size2.18 acres
SectorLand Use Designation? TP & SLPA
Currently on the Property
Vacant land
Growth PlanPlanned Growth Area
- Utilities
SewerWest Knox Utility District
WaterWest Knox Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the development plan for a restaurant and office building in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, subject to 8 conditions:
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Obtaining a variance from the Knox County Board of Zoning Appeals for a reduction in the number of required on-site parking spaces.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.
4. Obtaining approval for the resubdivision of the property.
5. A building permit being shall not be issued for this development until : a) Iron Gate Blvd. is constructed to a standard acceptable to the Knox County Department of Engineering and Public Works and opened for public use; b) the main driveway for Hardin Valley Crown Center Subdivision that borders this parcel on the north side is completed from Iron Gate Blvd. to the existing access easement/driveway located between the Bread Box Food Store and Bank East; and c) the improvements recommended in the Traffic Impact Study (Cannon & Cannon, Inc., dated 2/16/06) for the existing access easement out to Hardin Valley Rd., between the Bread Box Food Store and Bank East, have been constructed and approved by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
8. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.
Disposition Summary
APPROVE the development plan for a restaurant and office building in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, subject to 8 conditions:
Details of Action
1. Obtaining approval from the Tennessee Technology Corridor Development Authority (TTCDA) for the proposed development.
2. Obtaining a variance from the Knox County Board of Zoning Appeals for a reduction in the number of required on-site parking spaces.
3. Meeting all applicable requirements of the Knox County Zoning Ordinance.
4. Obtaining approval for the resubdivision of the property.
5. A building permit being shall not be issued for this development until : a) Iron Gate Blvd. is constructed to a standard acceptable to the Knox County Department of Engineering and Public Works and opened for public use; b) the main driveway for Hardin Valley Crown Center Subdivision that borders this parcel on the north side is completed from Iron Gate Blvd. to the existing access easement/driveway located between the Bread Box Food Store and Bank East; and c) the improvements recommended in the Traffic Impact Study (Cannon & Cannon, Inc., dated 2/16/06) for the existing access easement out to Hardin Valley Rd., between the Bread Box Food Store and Bank East, have been constructed and approved by the Knox County Department of Engineering and Public Works.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Connecting the development to sanitary sewer, as well as meeting other applicable requirements of the Knox County Health Department.
8. Installing all landscaping, as shown on the landscape plan, within six months of issuance of occupancy permits for the project, or posting a bond with the Knox County Department of Engineering and Public Works, to guarantee such installation.
With the conditions noted above, this request meets the requirements for approval in the PC (Planned Commercial) & TO (Technology Overlay) zoning districts, as well as other criteria for approval of a use on review.