Property Information
−
+
LocationNorthwest side of W. Beaver Creek Dr., northeast side of Brickyard Rd.
Commission District 6
Size10.09 acres
Sector
Currently on the Property
Residence and vacant land
Growth PlanPlanned Growth Area
- Utilities
ElectricityKnoxville Utilities Board
Natuarl GasKnoxville Utilities Board
SewerHallsdale-Powell Utility District
TelephoneMetro Group Bell South Telephone
WaterHallsdale-Powell Utility District
Case Notes
−
+
Staff Recommendation
APPROVE the Concept Plan subject to 9 conditions
1. Meeting all applicable requirements of the Knox County Zoning Ordinance.
2. Connection to sanitary sewer and meeting all other applicable requirements of the Knox County Health Department.
3. Provision of a street name which is consistent with the Uniform Street Naming and Addressing System in Knox County (County Ord. 91-1-102).
4. Design of the proposed entry gate location and turnaround area is subject to approval of the Knox County Department of Engineering and Public Works at the design plan stage of the subdivision. The gate shall also be designed to allow for access of emergency vehicles.
5. Prior to final plat approval, posting a bond with and in an amount acceptable to the Knox County Department of Engineering and Public Works to cover the cost of sidewalks along the property frontage of both W. Beaver Creek Dr. and Brickyard Rd. If the sidewalks are not constructed within five years of the issuance of the bond, the bond shall be released.
6. Meeting all applicable requirements of the Knox County Department of Engineering and Public Works.
7. Prior to final plat approval, establish a homeowners association for the purpose of maintaining the Joint Permanent Easement, stormwater drainage facilities and any other commonly held assets.
8. Placing a note on the final plat that all lots will have access only to the internal street system.
9. A final plat based on this concept plan will not be accepted for review by MPC until certification of design plan has been submitted to MPC staff
Disposition Summary
APPROVE the Concept Plan subject to 9 conditions